Importing an Activity Attribute Form

The Schedule Manager needs attribute forms to define the activities for a project schedule, including its start and end dates.

When creating new activities on the schedule sheet, Unifier opens this form as the General tab of the Activity Properties form.

Note: If there is no attribute form for the Schedule Manager, Unifier will create a default schedule sheet with the following columns: ID, Activity name, Start date, Finish dates, and Duration.

The Resource Manager and the Schedule Manager can work together for resource management. If you have deployed the Resource Manager, Unifier uses the Resource Assignment Attribute form as the Resource tab of the Activity Properties form.

To import and deploy a schedule attribute form or a resource assignment attribute form into Unifier Production environment, see Importing Configuration Packages.

See Also

Setting up the Schedule Manager

Additional Options for Setting Up the Schedule Manager

Create Schedule Sheet Templates

Deleting Schedule Sheets

Grant Schedule Manager and Custom Calendar Permissions to Users

Refresh Schedule Sheet Data

Updating Schedule Sheet Properties from Templates

Update Schedule Sheet Activities from Templates

Importing Schedule Files

Scope Management Setup

About Activity-level Editing

Permissions Setting for Activity Sheet

Activity Sheet Permissions in the System Activity Sheet Permissions Tab

Permissions for the System WBS Sheet