Note: If the user gets any of the permissions below, then the user can access the Activity Sheet node, in the User mode.
To enable the users create, modify, and view the activity sheets, where the user can manually create project schedules, go to the shell, Admin mode and from the left-hand Navigator click Access Control node to open the Access Control window.
In the Access Control window, the following Activity Sheet permissions will appear in the System Activity Sheet Permissions tab:
- Modify System Activity Sheet-All
To update the system activity sheet.
- Modify System Activity Sheet-Current
To update the system activity sheet.
- Modify System Activity Sheet-Current
- View System Activity Sheet-All
To view the system activity sheet.
- View System Activity Sheet-Current
To view the system activity sheet.
- View System Activity Sheet-Current
Before 21.4 Upgrade | After 21.4 Upgrade |
---|---|
Full Access | At module-level:
At sheet-level:
|
Send Data | At module-level:
|
Get Data - All | At module-level:
|
Get Data -Current | At module-level:
|
Modify -All | At module-level:
|
Modify - Current | At module-level:
At sheet-level:
|
View - All | At module-level:
At sheet-level:
|
View - Current | At module-level:
At sheet-level:
|