Update Schedule Sheet Activities from Templates

If you create project or shells with a template, you can update schedule sheet properties in the projects and shells from schedule sheets in the template. Updating Schedule Sheet Properties from Templates.

You can also update the activities on a schedule sheet by using a separate "linking" function in Unifier that links a schedule sheet to a template for the specific purpose of updating activities. This feature is also convenient if you have imported a schedule and want to push it to your projects or shells.

Note: Projects or shells that are in Inactive or View-Only status will not be updated.

See Also

Setting up the Schedule Manager

Additional Options for Setting Up the Schedule Manager

Importing an Activity Attribute Form

Create Schedule Sheet Templates

Deleting Schedule Sheets

Grant Schedule Manager and Custom Calendar Permissions to Users

Refresh Schedule Sheet Data

Updating Schedule Sheet Properties from Templates

Importing Schedule Files

Scope Management Setup

About Activity-level Editing

Permissions Setting for Activity Sheet

Activity Sheet Permissions in the System Activity Sheet Permissions Tab

Permissions for the System WBS Sheet

In This Section

What you can do with linked templates:

What you cannot do with linked templates:

Enable and Disable Schedule Sheet Linking

Link a Template to a Project or Shell Schedule Sheet

Update Linked Schedule Sheets from Project or Shell Templates

Unlink a Template From a Project or Shell Schedule

View Linked Schedule Sheets

Auto-Scheduling