Integrating a System Activity Sheet or Master Rate Sheet through Oracle Integration

After the connection between Unifier Essentials and Oracle Integration is established, you can use the OPC to Unifier Integration recipes to update the System Activity Sheet or the Master Rate Sheet (or both). The current recipes include Oracle OPC Unifier Activity Sync, Oracle OPC Unifier Resources Roles Sync, and Oracle Update OPC Activity Spreads to Unifier. You can initiate an update from within Unifier Essentials or in Oracle Integration.

When you use a recipe to update the System Activity Sheet for a project, it updates the sheet with the cost data, the Assignments (resources and roles), and the Activity Spread. Additionally, you can use the Primavera Cloud Schedule option to update multiple schedules. If you attempt to integrate an Oracle Primavera Cloud project that is already integrated with the same project or a different project in Unifier Essentials, the system notifies you that the integration cannot be added.

When you use a recipe to update the Master Rate Sheet, it updates the sheet with all the workspaces, resources, and roles from Oracle Primavera Cloud.

Note: You can use a Gateway Integration or a Primavera Cloud Integration with Unifier Essentials; you cannot use both. While one integration remains active, the other is unavailable.

To integrate a System Activity Sheet or Master Rate Sheet:

  1. Go to the Company Workspace tab and switch to Admin mode.
  2. In the left Navigator, click Integrations > Oracle Integration Cloud.
  3. In the Recipes tab, copy the applicable information from the POST field in the corresponding Oracle Integration recipe to the System Activity Sheet and Master Rate Sheet fields.
  4. When you are done, click Save.

To update the System Activity Sheet from within Unifier Essentials:

  1. Open the applicable project/shell and switch to User mode.
  2. In the left Navigator, click the project/shell name (Home icon).
  3. In the upper-right corner, click My Dashboard and select Details to open the Details form.
  4. Select the Primavera Cloud Integration tab.
  5. Click Add, and select Primavera Cloud Schedule.
  6. In the empty row that is added, complete the following fields:
    • Project ID: Enter the Oracle Primavera Cloud project ID. The ID must be unique to this shell and to Unifier Essentials. The ID cannot include the following characters: / \ : * ? " < > | ' =
    • Project Name: This field is optional.
    • Primavera Cloud Workspace ID: Enter the Oracle Primavera Cloud Workspace ID.

    The Integration Type field is completed by the system, based on the option you selected from the Add list.

  7. To add additional projects, click Add again, select Primavera Cloud Schedule, and complete the new row.
  8. When you are done, click Save.
  9. In the left Navigator, click Activity Manager > Activity Sheet.
  10. In the toolbar of the Activity Sheets log, click Get Data.
  11. In the Get Data dialog box, select the All Projects check box, and then clear any projects from the text box that you do not want updated.
  12. In the Type section, select Baseline.
  13. If you want to retain unreferenced data in the System Activity Sheet, clear the Remove Unreferenced Data check box in the Advanced Options section.
  14. When you are done, click OK.
  15. To view the status of the job, select the History tab in the right pane.

    You can click Refresh to update the information until the Status displays COMPLETED. If the Status is FAILED, select the line to view more information about the error that occurred.

To update the Master Rate Sheet from within Unifier Essentials:

  1. Go to the Company Workspace tab and switch to User mode.
  2. In the left Navigator, click Master Rate Sheet.
  3. In the toolbar of the Master Rate Sheet log, click Get Data .
  4. In the Get Data dialog box, select OIC, and click OK.
  5. In the Confirmation message, click Yes to continue.
  6. To view the status of the job, select the History tab in the right pane.

    You can click Refresh to update the information until the Status displays COMPLETED. If the Status is FAILED, select the line to view more information about the error that occurred.

See Also

Unifier Essentials and Oracle Primavera Cloud

Integrating Unifier Essentials with Oracle Primavera Cloud Overview

Permissions for Oracle Primavera Cloud Integration Settings

Sending and Receiving Cash Flow Data

Reviewing the Planned Budget and Submitting Results

Oracle Primavera Cloud Integration in Unifier Essentials Company

Oracle Primavera Cloud Integration in Unifier Essentials Shell

Oracle Primavera Cloud Integration and Unifier Essentials Cash Flow (User Mode)

Oracle Primavera Cloud Integration in Company Sponsored Shells

Sending Data from Cash Flow

Receiving Data from Primavera Cloud Project Cash Flows

Unifier Essentials and Oracle Integration



Last Published Tuesday, June 4, 2024