Activity Look Ahead Dashboard
Description: This dashboard provides a list of upcoming activities for the next 3 days, 1 week, 2 weeks, and for the next 30, 60, and 90 days.
Number of Canvases: 7
Default Canvas: Next 3 Days
Canvas/Dashboard Name: Activity Look Ahead Dashboard
Data Source(s): P6 - EPPM
Subject Area: P6 – Activity
Datasets: Not applicable
Dashboard
Canvases
Figure 15: Activity Look Ahead Dashboard - Next 3 Days
Figure 16: Activity Look Ahead Dashboard - Next 7 Days
Figure 17: Activity Look Ahead Dashboard - Next 14 Days
Figure 18: Activity Look Ahead Dashboard - Next 30 Days
Figure 19: Activity Look Ahead Dashboard - Next 60 Days
Figure 20: Activity Look Ahead Dashboard - Next 90 Days
Figure 21: Activity Look Ahead Dashboard - Activity Details
Table 23: Activity Look Ahead - Dimensions
Canvas | Dimension / Attribute | Subject Area / Dataset |
---|---|---|
All Canvas | Activity Status | P6 – Activity |
All Canvas | Critical | P6 – Activity |
All Canvas | Primary Resource | P6 – Activity |
All Canvas | Start | P6 – Activity |
Activity Details | Finish | P6 – Activity |
Activity Details | Activity Name | P6 – Activity |
Table 24: Activity Look Ahead – Measures
Canvas | Fact / Measure | Measure Type | Subject Area / Dataset |
---|---|---|---|
Next N Days | # of Activities | Fact | P6 – Activity |
Table 25: Activity Look Ahead – Filters
Canvas | Filter Type | Is Expression Filter | Dimension / Attribute / Measure | Subject Area / Dataset |
---|---|---|---|---|
Next N Days | Dashboard | No | Portfolio Name | P6 - Activity |
All Canvas | Dashboard | No | Project Name | P6 - Activity |
Next 3 Days | Dashboard | Yes | (CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,3,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))
| P6 - Activity |
Next 7 Days | Dashboard | Yes | (CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,7,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))
| P6 - Activity |
Next 14 Days | Dashboard | Yes | (CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,14,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))
| P6 - Activity |
Next 30 Days | Dashboard | Yes | (CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,30,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))
| P6 - Activity |
Next 60 Days | Dashboard | Yes | (CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,60,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))
| P6 - Activity |
Next 90 Days | Dashboard | Yes | (CAST("Primavera - Activity"."Dates - (Activity)"."Start" AS DATE) BETWEEN CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE) AND TIMESTAMPADD(SQL_TSI_DAY,90,CAST("Primavera - Activity"."Dates - (Project)"."Data Date" AS DATE)))
| P6 - Activity |
Table 26: Activity Look Ahead – Calculated Members
Calculated Member | Expression | Source | Subject Area / Dataset |
---|---|---|---|
Schedule % Complete (PRCNT) | "Primavera - Activity"."Percent Complete"."Schedule % Complete" / 100
| Derived From Fact | P6 - Activity |
Related Topics
Data Visualizations Using P6 EPPM Data
Earned Value and Risk Analysis Dashboard
Overview - Portfolio, Risk, EV
Key Milestones Tracking Dashboard
Integrated Schedule Delivery KPI Dashboard
Shutdown / Turnaround / Outage Dashboard
CPI, SPI, and Labor Units Dashboard
Project Risk - Cost Overview Dashboard
Project Health Assessment Dashboard