Creating Milestone Tasks

Project milestones are used to mark a point in your project, usually completion of a set of tasks or as a project health check to determine if you’re on schedule.

When creating a milestone task, you cannot assign a resource, enter estimated work, or a Finish No Later Than (FNLT) constraint. When viewing a project Gantt chart or schedule, milestone tasks are differentiated from regular project tasks.

To create a project milestone:

  1. Go to Lists > Relationships > Projects.

  2. Click the name of the project you want to edit.

  3. On the Schedule tab, click New Milestone.

    NewMilestoneButton
  4. Enter a name for your milestone.

  5. Click the Predecessors tab.

  6. Select a predecessor task and type.

  7. Click Add.

  8. Continue adding any additional predecessors, when you have finished, click Save.

Converting Milestone Tasks to Project Tasks

A milestone can be converted to a project task by adding a positive number of estimated work or tracking time against the milestone.

Note:

You can edit a milestone and assign a resource with 0 hours of estimated work without converting the milestone to a project task. However, if the resource tracks time against the milestone it will be converted to a project task.

A Project task can also be converted to a milestone by removing positive estimated work and any FNLT constraint.

Related Topics

Project Tasks
Project Task Records
Project Task Attributes Table
Identifying Parent Tasks
Scheduling Project Tasks
Importing Project Tasks from Microsoft Project

General Notices