Scheduling Project Tasks

NetSuite prepares a system-calculated schedule for each project based on project start date or end date, task durations, predecessors, constraints, and resource work calendars. The schedule drives planning, billing, and management for the entire project.

For forward scheduling projects, the project Start Date sets the date from which the project schedule is calculated. For backward scheduling projects, the project End Date sets the date from which the project schedule is calculated.

To view the schedule for a project, go to Lists > Relationships > Projects and click View next to the project. On the project record, the Schedule subtab is the top subtab.

Resource Assignment and Project Scheduling

Project scheduling is also based on resource and work data entered on task records. The schedule is based on the duration of the tasks. Task duration is calculated as [estimated work x units] for all task resource rows and helps determine the start and end dates for each task.

For example, a task requires 16 hours of work. Two resources are assigned to the task, each set to work at 100% capacity and for 8 estimated hours. Each resource is assigned to the default work calendar of eight hours per day, Monday through Friday. The task is scheduled across two calendar days, so the project work schedule is 2 days in duration. The schedule also takes into account any time off requested by the assigned resources.

Note:

The task duration calculation is also based on the task relationships. See Adaptive Scheduling below.

Depending on the scheduling method, the start date or end date of a project task is calculated by assessing the number of hours assigned to each task resource. For each assignment, the resource's work calendar is used to add the specified number of hours to the start date-time or end date-time to arrive at the tasks dates. If the start date or end date of your project changes, NetSuite automatically updates the task dates based on the scheduled tasks. If time off is submitted after the creation of the schedule, the project must be recalculated for adjustments to occur. For more information on scheduling methods, see Project Scheduling Methods.

The total number of hours for the project task is calculated by summing the hours assigned to each resource.

Work calendars

Work calendars define the work capacity for resources. Then, that capacity determines when tasks can be scheduled. For details, read Project Resource Work Calendars.

Creating Planned Time Entries

When you create a project task, you enter the resource work capacity as percentage of available scheduling time in the Units column. NetSuite uses the work capacity and work calendars for resources assigned to project tasks to create the project schedule and generate planned time entries. If you create planned time entries for a project, NetSuite limits the number of time entries that can be created.

In order to prevent projects with excessive number of tasks and time entries, the following rules apply:

Project tasks

When assigning a resource to a project task, the resource capacity or units must be 5% or greater. The estimated work for the resource must be 2080 hours or less.

Depending on the work calendar parameters, possible planned time entries vary. The minimum planned time entry possible depends on the hours per day in the work calendar. For resources assigned to a work calendar with eight hour work day, the minimum planned time entry cannot be less than 24 minutes. The smallest planned time entry possible is 3 minutes (5% of 1 hour, the minimum hours per day allowed in work calendar).

The maximum number of planned time entries per task that can be created for a resource is 260. This is the maximum number of work days a resource can be assigned to work on a task.

Projects

The total number of planned time entries for all project resources must be 5200 or less. The total amount of work days scheduled for a project cannot exceed 20 person years of work.

Adaptive Scheduling

Project tasks are capable of adaptive scheduling. This means, when the current project schedule is viewed, the project schedule accurately reflects necessary changes to the project.

For example, when a project plan is initially created based on task dependencies and resource work calendars, the schedule represents an idealized estimate. This initial estimate does not reflect any actual project work if no actual time has been entered against the project from resources working on the project.

After work on the project begins and progresses, resources enter time worked on the project. After resources enter time against a project, some aspects of project tasks may begin to shift. Aspects that may change include the following:

For example, the work for TaskOneA is 40 hours: 8 hours per day, Monday through Friday. If a resource assigned to the task enters 4 hours for Monday, then the schedule automatically recalculates so that the project plan shows 4 hours of actual time worked on Monday, 8 hours of planned work scheduled Tuesday through Friday, and 4 hours of planned work scheduled the following Monday for a total of 40 hours.

Tasks with predecessor relationships are set to start based on the start and finish of other tasks. Then, if the duration of one task must change, all tasks related to it may be recalculated to show an updated duration and new start and end dates. For more information, read Predecessor-successor relationships below.

The Time subtab on task records shows Planned Time and contributes to a real-time picture of project schedule.

Task setup and scheduling

The characteristics of a project task are largely derived from its relationship to other tasks for the project. Task relationships can be one of the following:

Tasks for a project can be arranged in a hierarchy by assigning parent-child relationships. For example, you may create Task One. Then, you create tasks TaskOneA, TaskOneB, and TaskOneC, and assign Task One as the parent task for all three tasks. Identifying Parent Tasks are tasks that have child tasks assigned to it.

The parent task, Task One, is also known as a summary task. The data values shown on a summary task are the rolled up values of its children. For example, a summary task's start date is the earliest start date of its child tasks, and its end date is the latest end date of its child tasks. The summary task's work is the sum of the work of its leaves.

Predecessor-successor relationships

In addition to a hierarchical structure, project tasks relationships can also be defined in terms of dependency. For each task, you can define how that task relates to other project tasks based on when the task should start. Each task is a predecessor or a successor, even if the task runs concurrent to other tasks.

For example, the completion of TaskOneB requires components that are assembled during TaskOneA. Therefore, TaskOneA is a predecessor of TaskOneB. TaskOneB cannot begin until TaskOneA is completed.

Dependency types that can be assigned on tasks are

Some data on a project task are calculated using input from its dependency relationships. The start date of a project task is the latest end date of all predecessors in the start-to-finish dependency case and is the last start date of all its predecessors in the start-to-start case.

Project tasks that have no predecessors start on the start date of the project.

Related Topics

General Notices