Time Fences
Materials planners can use planning and demand time fences to protect the materials plan. Time fences keep existing orders from changing, prevent disruptions, and help refine demand requirements in short-term materials planning.
The NetSuite Supply Planning (MRP) solution replaces Time-Phased Planning and offers more features and better performance.
New customers should use the Supply Planning (MRP) solution. Existing customers should plan to move from Time-Phased Planning to MRP.
If you use Demand Planning, you can set up Demand Time Fences and Planning Time Fences.
-
Demand Time Fences – A point in time, or boundary, in the master schedule when the forecast is no longer included in total demand and projected available inventory calculations. Within this point, only customer orders are considered.
-
Planning Time Fence – A point in time, or boundary, in the master schedule when changes to the schedule might adversely affect component schedules, capacity plans, customer deliveries, and cost.
Related Topics
- Demand Time Fences
- Planning Time Fence
- Setting Time Fence Preferences
- Setting Up Demand Planning
- Demand Planning on Item Records
- Calculating Item Demand
- Monitoring the Demand Plan Status
- Viewing, Editing, and Deleting a Demand Plan
- Manually Entering an Item Demand Plan
- Creating Item Supply Plans
- Monitoring the Supply Plan Status
- Viewing, Editing, and Deleting a Supply Plan
- Manually Entering an Item Supply Plan
- Creating Orders from Supply Plans
- Reporting on Demand Planning
- Distribution and Demand Planning
- Demand Planning and Inventory Allocation
- Demand Planning