Demand Planning on Item Records

To use Demand Planning for an item, set the replenishment method to Time Phased on the item record. Items with MPS/MRP replenishment methods can be used with demand plans. They cannot be used with time-phased supply plans.

Important:

Did you know that the NetSuite Supply Planning (MRP) solution replaces Time-Phased Planning, with more features and better performance?

New customers should use the new Supply Planning (MRP) solution. Existing customers should develop a plan to move from Time-Phased Planning to the new solution.

To use Demand Planning for assembly items, enable the Work Orders feature. For more information, see Setting Up Demand Planning.

Before you set up an item for demand planning, you must specify the replenishment method.

Related Topics

General Notices