Report Tab of the Check Schedule Dialog Box
Overview
Use this tab to view potential issues in a schedule. For example, the report might identify missing logic or a large number of constraints in the schedule.
Screen Elements
The report elements available depend on the parameters selected when the Check Schedule job was initiated. Click one of the links below for detailed screen definitions:
- Projects Checked Section of the Schedule Check Report Dialog Box
- Projects Checked Have Links to the Following Closed Projects Section of the Schedule Check Report Dialog Box
- Check Summary Section of the Schedule Check Report Dialog Box
- Relationships - Activities Missing Predecessors or Successors Section of the Schedule Check Report Dialog Box
- Dangling Start - Activities With Start Dates That Are Not Driven by Predecessors Section of the Schedule Check Report Dialog Box
- Dangling Finish - Activities With Finish Dates That Do Not Drive Successors Section of the Schedule Check Report Dialog Box
- Negative Lags - Relationships With a Lag Duration of Less Than 0 Section of the Schedule Check Report Dialog Box
- Lags - Relationships with a Positive Lag Duration Section of the Schedule Check Report Dialog Box
- Long Lags - Relationships with a Lag Duration Greater Than 352 Hours Section of the Schedule Check Report Dialog Box
- Relationship Types - The Majority of Relationships Should be Finish to Start Section of the Schedule Check Report Dialog Box
- Hard Constraints - Constraints That Prevent Activities Being Moved Section of the Schedule Check Report Dialog Box
- Soft Constraints - Constraints That Do Not Prevent Activities Being Moved Section of the Schedule Check Report Dialog Box
- Large Float - Activities with a Total Float Greater Than 352 Hours Section of the Schedule Check Report Dialog Box
- Negative Float - Activities with a Total Float Less Than 0 Section of the Schedule Check Report Dialog Box
- Large Durations - Activities That Have a Remaining Duration Greater Than 352 Hours Section of the Schedule Check Report Dialog Box
- Invalid Progress Dates - Incomplete Activities Before the Data Date Section of the Schedule Check Report Dialog Box
- Invalid Progress Dates - Activities with Actual Dates After the Data Date Section of the Schedule Check Report Dialog Box
- Resource/Cost - Activities That Do Not Have an Expense or a Resource Assigned Section of the Schedule Check Report Dialog Box
- Late Activities - Activities Scheduled to Finish Later Than the Project Baseline Section of the Schedule Check Report Dialog Box
- BEI - Activities with No Project Baseline Finish Date Section of the Schedule Check Report Dialog Box
- Links to Closed Projects - Activities with Links to Closed Projects Section of the Schedule Check Report Dialog Box
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.