Migrating InForm studies to a new machine

You can migrate any supported InForm 5.5.x.x, 6.0.x.x, 6.1.0.x, or 6.1.1.x study to a new machine.

You can perform an in-place upgrade from InForm 6.2.x.x, 6.3, or 6.3.1. For more information, see Running an in-place upgrade. Oracle does not support an in-place upgrade for any InForm release prior to 6.2.x.x.

Note: Depending on the InForm version you are migrating from, some steps may not be required.

  1. Install and configure the InForm 6.3.1.1 software.
  2. Copy the backup files to the InForm 6.3.1.1 application server.
  3. Make updates to the Windows registry settings.
  4. Create tablespaces other than INFORM.
  5. Import the InForm study DMP file.
  6. Set up InForm customer-defined databases.
  7. Set up a randomization source for a study.
  8. Install the Central Designer certificate.
  9. Perform the final study configuration.
  10. Install or upgrade the InForm Adapter software.
  11. Start the InForm studies.
  12. Set the password for the system user.
  13. Import the custom events created in previous releases into the study in Central Designer.

    Note: This step is required only for studies with custom events.

  14. Create the Central Designer study deployment.
  15. Install the Central Designer deployment package.
  16. Clear the Client browser cache.