Power On the Server

As soon as the power cords are connected, standby power is applied and the green Power/OK status indicator on the server front panel blinks. Depending on the configuration of the firmware, the system might boot. If it does not boot, follow this procedure.

  • Power on the server by performing one of the following:
    • Press the Power button on the server front panel.

      or

    • Log in to the Oracle ILOM web interface, click Host Management → Power Control and select Power On from the Select Action list.

      or

    • Log in to the Oracle ILOM command-line interface (CLI), and type the following command at the Oracle ILOM prompt:

      -> start /System

    When the server is powered on and the power-on self-test (POST) code checkpoint tests have completed, the green Power/OK status indicator on the front panel lights and remains lit.