Installation Task Overview

Steps
Description
Links
1.
Review the Product Notes for any late-breaking news about the server.
2.
Review the server features, specifications, and site requirements.
3.
Confirm that you received all of the items you ordered.
4.
Learn the server features, controls, and LEDs required for installation.
5.
Take safety and ESD precautions and assemble the required tools.
6.
Install any optional components into the server.
7.
Install the server into a rack.
8.
Attach data and management cables to the server.
9.
Connect the power cords to the server, configure the Oracle ILOM on the SP, power on the server for the first time, and set up the operating system.