The following explains the toolbar options in a created activity sheet, in default view:
Toolbar | Description |
---|---|
Add | To add a new row. The row will have the Activity ID field value pre-populated with the sequence number specified in the activity sheet properties. The Activity Name field is displayed as required and other required columns will be highlighted with red triangle, on the right-hand side corner. Upon selecting Save All, the required fields will show as errors in the first column (similar to manage rows in the cost sheet).
Note: The activity sheet shows the flat list of activities. Any user with edit permissions would be able to add and update the activities to the activity sheet. |
Schedule | To enable the scheduling in the activity sheet, once you add the activities, and updating the activity schedules like planned, actual dates, duration, and so forth. It also enables you to remove the activities. All of the dependent activities will be rescheduled based on the data date specified in the schedule. If you select this option in a blank sheet, then Unifier displays this message: There are no activities in the sheet to be scheduled. |
View | Same as in the System Activity Sheet, the View drop-down list displays the system-defined view 'Default' and 'WBS View', by default. You can create and manage views in the activity sheet.
You can add activities and change column structure in the Default view, also. Similar to the other activity sheets, the data creation (both rows and columns) will be available in the default view. |
Edit View Settings | To edit the user-defined views. |
Actions | If you (the user) have at least Edit Data permission for manual activity sheet, then you can use the Actions option and perform the following:
See the "Actions Option" topic, below, for more details. |
Refresh | All of the existing export and import options available for CBS Code activities and assignments will be seen in the Menu Options. To refresh the contents of the activity Sheet. Note: If there are unsaved changes in the sheet, Unifier displays this message: You have unsaved changes in the sheet. These will be lost on refresh. Do you want to proceed? If you select 'Yes', then the activity sheet should be refreshed; otherwise, refreshing of the activity sheet will not happen. |
The following printing options are available:
| |
Find on Page | To conduct search in the activities and other attributes within the activity sheet. |
Search | To search the activities based on search parameters that are defined in uDesigner. Note: If there are unsaved changes in the activity sheet and you click 'Search', the search result will include the unsaved rows. |
Menu Options (the three horizontal line icon with down-arrow) | There will be no option for updating the CBS Code for Activities or Assignments. Any Activity Sheet defined in project, where the logged user have at least edit data permission to the sheet, has the following options:
See the "Menu Options" topic, below, for more details. |
Gantt
| Once you click Gantt, the following toolbar options become available:
The Show drop-down field will be editable once you select Gantt from the toolbar. This drop-down has the following options:
Dates and Numeric values displayed in tool-tip are based on the user preference set at company-level. For more details about Gantt view, see "Gantt View" below. |
Switch to Current Project View | Enables you to see the current project. |
Switch to Baseline Project View | Enables you to:
|