Executing the Data Load Rule

As part of the budget data import implementation, you need to verify that the data load rule you created in Adding a New Data Load Rule runs successfully in Data Management.

To execute a data load rule:

  1. In your Planning and Budgeting environment, click the Navigator icon This icon takes you to the main menu in your Oracle EPM Planning application.. Then, under Integration, click Data Management.

  2. On the Workflow tab, under Data Load, select Data Load Rule.

  3. In the Point of View bar at the bottom of the page, verify that you are using the Point of View specified in Adding a New Data Load Rule.

  4. In Data Rule Summary, select the data load rule you created in Adding a New Data Load Rule, and then click Execute.

  5. In the Execute Rule popup window, make any necessary changes, and then click Run.

  6. To watch the progress of the data load rule execution, go to Process Details on the Tasks pane.

  7. If the data load rule has been executed successfully, you can do any of the following:

    • In Process Details, scroll right to the Output File column, and download the execution result.

    • Go to Application > Overview > Actions > Inbox/Outbox Explorer to access the CSV file generated by this data load rule.

    • Execute this data load rule from NetSuite. If the job is executed successfully, NSPB Sync downloads the CSV file from Inbox/Outbox Explorer, and the post-processing plug-in processes the budget data in NetSuite.

For general information and additional setup, see the Oracle Help Center topic Managing Data Load Rules.

Related Topics

Budget Data Import Using Data Management
Creating a Target Application
Adding the Import Format
Adding a New Location
Adding a New Data Load Rule
Adding Data Load Mapping

General Notices