3.1.2 Maintenance Window Tasks

Table 3-3 Timeline table for Full upgrade of ELAP

LSMS
Procedure Task Time Task Start time (min)

SM Migration, Appendix D

Disconnect NPAC from LSMS

5

0

Procedure 4

*LSMS Servdi Backup

170

175

*LSMS Servdi backup time will vary according to the data on LSMS. This has to be done simultaneously while IPMing the ELAP servers.

Table 3-4 Timeline table for Full upgrade of ELAP

ELAP A   ELAP B
Procedure Task A Task Start time (min) B Task Procedure

Procedure 5

Backup EuiDB with

MyISAM engine and InnoDB engine

15

15

     

Procedure 6

Disconnect ELAP from

LSMS

5

20

     
     

25

45

IPM MPS server with TPD 8.10.x

Procedure 7

     

70

10

Pre-install configuration

Procedure 8

     

80

30

ELAP installation steps

Procedure 9

     

110

10

Configure Network for Backup transfer

Procedure 10

Procedure 15

Transfer backup to local B

5

115

     

Procedure 7

IPM MPS server with TPD

8..x

45

120

     

Procedure 8

Pre-install configuration

10

165

     

Procedure 9

ELAP installation steps

30

175

     

For Telco Switch-Procedure 11

For Cisco Switch- Procedure A.2

Switch Configuration

30

205

     

Procedure 12

*Configure NTP server

5

210

     

Procedure 13

Initial Network Configuration

10

220

     

Procedure 14

Verify Configurations

5

225

     
     

230

5

Transfer backup to local

A

Procedure 15

Procedure 16

Restore EuiDB

5

235

     

Procedure 17

SSH key exchange between ELAP and LSMS

5

240

     

Procedure 18

Repoint LSMS to ELAP VIP

15

255

     

Procedure 19

Transfer Servdi Image To

ELAP

5

260

     

Procedure 20

Restore Servdi

15

275

     

SM Migration, Appendix E

Connect NPAC to LSMS

5

280

     

Procedure 21

Post Upgrade Syscheck

5

280

5

Post Upgrade Syscheck

Procedure 21

Procedure 22

Accept The Upgrade

5

285

5

Accept The Upgrade

Procedure 22

* After ELAP installation, switch configuration is done before configuring NTP server and initial configuration, it will take an extra 30 minutes to configure the switches. Follow Procedure A.1 and Procedure A.2 for Cisco switch configuration steps and Procedure 11 for Telco switch configuration.

Note:

After accepting upgrade on ELAP, the SCCP cards at EAGLE should be initialized to load the ELAP DB. Follow Procedure 25.