Updated: February 2016
 
 

Unpack and Inspect the Machine


Caution

Caution  -  Rocking or tilting the rack on the shipping pallet can cause it to fall over and cause serious injury or death.


  1. Use a No. 2 Phillips screwdriver to remove the shipping brackets from the lower front edges of each rack.
  2. Check the rack for damage.
  3. Check the rack for loose or missing screws.
  4. Check the rack for the ordered configuration.
    • Refer to the Customer Information Sheet (CIS) on the side of the packaging.

    • Two wrenches are included. The 12-mm wrench is for the cabinet leveling feet. The 17-mm wrench is for the bolts that hold the rack to the shipping pallet.

    • Two keys are included for the cabinet doors.

    • A box of other hardware and spare parts is included in the shipping carton. Note that some of these parts are not required for this installation.

  5. Check that all cable connections are secure and firmly in place:
    1. Check the power cords.

      Ensure that the correct connectors have been supplied for the data center facilities power source.

    2. Check the network data cables.
  6. Check the floor tile preparations, if applicable.

    See Perforated Floor Tiles.

  7. Check the data center airflow around the installation site.

    See Heat Dissipation and Airflow Requirements for more information.