Understanding the Installation
Understanding Management and Power Cabling
Single-Switch Location Guidelines
Attach the Rails to the Switch
Attach Telco Adapters to the Rack Slides
Install the Switch Into the Rack
Install the Air Duct and Front Support
Attach Data and Management Cables
Prepare the Front Support and Small Air Duct
Verify the DHCP-Assigned IP Address and Host Name
Configure Network Management From the CLI (SER MGT)
Log Into the Oracle ILOM Web (NET MGT)
Log Into the Oracle ILOM CLI (NET MGT)
Log Into the Oracle ILOM CLI (SER MGT)
Change a SEFOS User Privilege Level
Configure Network Management From the Web Interface
Configure Network Management From the CLI
Log Out of the Oracle ILOM CLI
Configuring the SEFOS Environment
Configuring the Switching Feature
Configuring the Routing Feature
Check Switch Status (Oracle ILOM)
Note - The rack slides might have a telco adaptor attached, and so would look different than those in these illustrations. However, the procedure to attach the rack slides is the same.
Rack slide assembly (2)
CMA assembly
M6 cage nuts (12)
M6x14 mm Philips screws (10)
Note - On the hot aisle, install three cage nuts on each post. On the cold aisle, install two cage nuts on each post for telco racks, or three cage nuts on each post for any other rack
The green tab is toward the hot aisle.