Install the Battery

  1. Unpack the replacement battery.
  2. Press the new battery into the battery retainer with the negative side facing inside the storage server chassis.
  3. Return the storage server to operation.
    1. Lower the air baffle to the installed position.
    2. Install the storage server top cover.

      See Install the Storage Server Top Cover.

    3. Return the storage server to the normal rack position.

      See Return the Storage Server to the Normal Rack Position.

    4. Reconnect the power cords to the storage server power supplies, and power on the storage server.

      See Reconnect Power and Data Cables and Power On the Storage Server. Verify that the power supply AC OK LED is lit.


      Note -  If the service processor is configured to synchronize with a network time storage server using the Network Time Protocol (NTP), the Oracle ILOM SP clock will be reset as soon as the storage server is powered on and connected to the network; otherwise, proceed to the next step.
  4. If the service processor is not configured to use NTP, you must do one of the following:
    • Reset the Oracle ILOM SP clock using the Oracle ILOM CLI or the web interface.

      For instructions, refer to the Oracle Integrated Lights Out Manager (ILOM) 3.2 Documentation Library at http://www.oracle.com/goto/ilom/docs.

    • Use the BIOS Setup Utility to reprogram the host clock.

      For the BIOS Main menu that supports this procedure, refer to the Oracle X5 Series Servers Administration Guide at http://www.oracle.com/goto/x86admindiag/docs.