Access Route and Data Center Checklist
Review the following facility checklist before installing the server:
|
|
|
|
|
Has the access route been
checked for clearances of the packaged
equipment?
|
|
|
|
|
Do all the doors and entry ways conform to the width and height
requirements for transportation, including the width of the unpacked
unit?
|
|
|
|
|
Are there any ramps, stairs, or thresholds that are in the moving
path for the new hardware?
|
|
|
|
|
Have you confirmed that the access route is free of any obstacles
that would expose the device to shock?
|
|
|
|
|
If there are stairs, then is a loading elevator accessible for
moving the equipment?
|
|
|
|
|
Has the rack location been allocated?
|
|
|
|
|
Is there a vacant space in the rack for the new server?
|
|
|
|
|
Does the floor layout meet the equipment maintenance access
requirements?
|
|
|
|
|
Is there adequate space available for server maintenance?
|
|
|
|
|
Have cabinet stabilization measures been considered?
|
|
|
|
|
Will the hardware location require any non-standard cable
lengths?
|
|
|
|
|
Is the floor to ceiling height a minimum of 2914 mm or 2.9 m (9.6
feet)?
|
|
|
|
|
Is the depth of the raised floor a minimum of 460 mm (18
inches)?
|
|
|
|
|
|