Future Period Planning: Entering and Editing Data

Entering differing values for Planned Units and Remaining Early Units for the same time period.

For assignments on activities that have not started, if the Link planned and at completion for not started activities option is selected on the Calculations tab of the project preferences, the total values of the Planned Units and Remaining Early Units for the assignment will always be equal. If this setting is not marked, you can enter different values for the same future period in the Planned Units and Remaining Early Units fields; in this case, the total values for each field are calculated independently for the assignment.

For activities that are in progress, you can always enter different future period values in the Planned Units and Remaining Early Units fields.

Entering data by financial period.

You can enter data by financial period for the range of financial period dates defined in the Financial Periods calendar assigned to the project. For example, if you have defined weekly financial periods from January 1st, 2015 to December 31st, 2016, you can enter data in weekly financial periods beginning on or after January 1st, 2015, and ending on or before December 31st, 2016. You should set the Timescale to Financial Period in the Usage Options dialog box to enter data by financial periods.

Overallocating resources and roles when entering future period values.

If the resource or role on the assignment has valid worktime for a time period, you can enter more units for the time period than the resource or role's Units/Time would allow, thus overallocating the resource or role.

Representing planned work for time periods where no work is planned.

You can leave a time period blank (or enter zero) to represent a period when no work is planned. P6 treats a blank value the same as a zero value.

Entering future period values for an assignment that already has an assigned resource curve.

You can enter future period data when a resource assignment already has a resource curve assigned. In this case, P6 will change the resource curve to Manual. To simplify the process of planning future period assignments, you can apply a resource curve to the assignment that has a similar resource distribution to the distribution you intend to plan, then make any necessary modifications to the future period values.

Note: When you apply a resource curve to an assignment and then modify future period values for that assignment, the resource curve is removed from the assignment when the assignment is designated as a Manual curve. If you then reapply a resource curve, the data you entered into future periods will be lost and future period data will be spread according to the resource curve you select.

Entering zero units.

If you enter zero into the first future periods of an assignment, P6 will interpret the zero units as lag and reduce the duration of the assignment. If zero is entered into the first Planned Units future periods, P6 will decrease the Planned Units and Planned Duration of the assignment. If zero is entered into the first Remaining Early Units future period, P6 will decrease the Remaning Early Units and Remaining Duration of the assignment.

For assignments to not started activities, if the Link planned and at completion for not started activities project option is not selected and you enter zero into the first future periods for an assignment, lag is added to both the Planned Start and Remaining Start dates. This occurs regardless of the field in which you enter the leading zero (Planned Units or Remaining Units) because the Planned Start and Remaining Start dates must be the same for activities that are not started.

If you enter a zero value in between non-zero values for an assignment, P6 considers the zero value to be part of the planned resource distribution.

When you enter zero in the last future periods for an assignment,P6 does not store the zero value as part of the manual curve. These zero values will not add to the duration of the assignment.

Entering negative values.

Negative values are valid when planning future periods if the total Planned Units or Remainign Early Units value for the assignment is negative.

Future Period Planning and Suspend and Resume dates.

You can enter or edit values in future periods between Suspend and Resume dates if the suspended time has not been scheduled (in other words, the project has not been scheduled since the suspend and resume dates were added to the activity).

When the project is scheduled, the suspend and resume dates for the activity are scheduled accordingly and you can no longer enter or edit data in future periods which are scheduled to be suspended. Units which have been entered against a resource assignment between the suspend and resume dates of an activity are moved to the resume date when the project is scheduled.

Changing the view timescale after entering future period data.

If you change the view timescale to a smaller unit after entering future period data (for example, changing the timescale from showing months to showing weeks) future period values will be spread linearly across the smaller timescale periods. If you change the view timescale to a larger unit, future period data is aggregated into the larger timescale periods.

Related Topics

Reference Topics

P6 Team Member Interface Field Names

Action Required for Document Reviews Toolbar

Action Required for Workflows Toolbar

Activity Count Columns of the Activity Table

Activity Steps Columns of the Activity Table

Applying Actuals Based on the Auto Compute Actuals Method

Applying Actuals Based on the Timesheets Method

Available Columns of the Activities Page

Available Columns of the Assignments Detail Window of the Activities Page

Available Columns of the Assignments Page

Available Columns of the EPS Page

Baseline Columns of the EPS Table

Bubble Chart Settings Area

Budget Columns of the EPS Table

Calendar Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Cost Columns of the EPS Table

Costs Columns of the Activity Table

Costs Columns of the Assignments Table

Dates Columns of the Activity Table

Dates Columns of the Assignments Table

Dates Columns of the EPS Table

Default Settings for Views

Document Search Criteria

Document Security (Reference)

Durations Columns of the Activity Table

Durations Columns of the Assignments Table

Durations Columns of the EPS Table

Earned Value Columns of the Activity Table

Earned Value Columns of the EPS Table

Errors Section of the Leveling Report Log

Future Period Planning: Deleting, Copying, Pasting, and Replacing Data

Future Period Planning: Importing and Exporting Data

Future Period Planning: Miscellaneous Information

Future Period Planning: Settings

Future Period Planning: Troubleshooting

Future Period Planning: Updating Projects

General Columns of the Activity Table

General Columns of the Assignments Table

General Columns of the EPS Table

Histogram Chart Settings Area

Level Resources Dialog Box (Reference)

Lists Columns of the Activity Table

Multiple Float Paths of the Activities Table

My Documents Portlet Toolbar

My Reviews Toolbar

My Workflows Toolbar

Number of Activities Columns of the EPS Table

Pages Supporting Filters

Percent Complete Columns of the Activity Table

Percent Complete Columns of the Assignments Table

Percent Complete Columns of the EPS Table

Performance Status Calculations

Personal Information Tab of the My Preferences Page

Pie Chart Settings Area

Portfolio Analysis Settings Area

Portfolio Analysis Toolbar

Portfolios Navigation Bar

Pre-response Thresholds (Risks)

Preferences Columns of the EPS Table

Private Documents Toolbar

Publication columns of the EPS Table

Recent Documents Toolbar

Resource Columns of the Assignments Table

Resources Navigation Bar

Risk Exposure (Pre-response)

Risk Exposure Calculations

Risk Scoring Method Description

Scorecard Settings Area

Set the Industry Type (P6 EPPM Only)

Standard Work Week Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Summarized, Published, and Live Data Usage in P6

Summary Columns of the EPS Table

Summary Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Team Member and P6 Mobile tab of the Consent Notice Page

Timesheet Feedback Columns of the Activity Table

Units Columns of the Activity Table

Units Columns of the Assignments Table

Units Columns of the EPS Table



Last Published Wednesday, July 10, 2024