SPARC M8 and SPARC M7 Servers Installation Guide

Exit Print View

Updated: September 2017
 
 

Site Preparation Checklist

Before installing the server, ensure that the following requirements are satisfied.

Requirement
Question
Check
Training
Have the administrators and installers reviewed the documentation and completed the necessary training courses?
The server documentation pages, which include links to Oracle University training courses, are at:
image:Check box icon
Configurations
Have you determined the server components and configuration?
image:Check box icon
Have you determined the total number of servers to be installed?
image:Check box icon
Access route
Have you inspected and prepared the entire access route from the loading dock to the server's final installation site?
image:Check box icon
Does the access route provide sufficient space for transporting a packaged server?
image:Check box icon
Have you protected the access route by covering it with fiberboard or similar material?
image:Check box icon
Installation site
Does the server's installation location meet all space requirements?
image:Check box icon
If you are installing a stand-alone server, is your rack compatible with the included rackmount kit?
image:Check box icon
Is the data center or server room located in a secured location?
Refer to the SPARC M8 and SPARC M7 Servers Security Guide for more information.
image:Check box icon
If necessary, have you prepared the installation site floor for subfloor cabling?
image:Check box icon
Power
Do you understand the operating voltages and electrical current levels required to power the server and its peripherals?
image:Check box icon
Are there enough power outlets available to power the server and peripherals?
See Understanding Power Cord-to-PDU Relationships or your rack's PDU documentation.
image:Check box icon
Have you prepared two facility power grids to power the server?
image:Check box icon
For rackmounted servers, have you prepared the appropriate facility power outlets for the PDU power cords? Are all of these outlets grounded?
See:
image:Check box icon
For rackmounted servers, are there circuit breakers for each PDU power cord and do they meet the capacity requirements?
image:Check box icon
Requirement
Question
Check
Operating environment and cooling
Does the data center meet the temperature and humidity requirements?
image:Check box icon
Does the installation site environment provide adequate ventilation and airflow to cool an operating server?
See:
image:Check box icon
Have you taken measures to prevent airborne contaminates from entering the installation site?
image:Check box icon
Unpacking
Have you acclimated the packaged server to the data center environment prior to unpacking it?
image:Check box icon
Have you set aside an area, away from the installation location, where you can safely unpack the server?
image:Check box icon
Data connections
Do you clearly understand the data connections required for setting up the server and connecting it to the network?
image:Check box icon
Have you prepared network addresses for all data connections?
See:
image:Check box icon

Related Information