JavaScript is required to for searching.
Skip Navigation Links
Exit Print View
Oracle SuperCluster M6-32

Owner's Guide: Installation

search filter icon
search icon

Document Information

Using This Documentation

Product Documentation Library

Feedback

Installing SuperCluster M6-32

Hardware Installation Overview

Weight Specifications

Hardware Installation Task Overview

Hardware Installation Documents

Preparing the Site (Storage Rack and Expansion Racks)

Prepare the Site for the Racks

Storage Rack Components

Physical Specifications

Reviewing Power Requirements

PDU Power Specifications

Facility Power Requirements

PDU Thresholds

Preparing for Cooling

Heat Dissipation Specifications

Airflow Requirements

Perforated Floor Tiles

Environmental Specifications

Preparing the Network

Network Topology

Network Infrastructure Requirements

Compute Server Default Host Names and IP Addresses

Install Cable Drops

Prepare DNS

Cabling SuperCluster M6-32

Compute Server Network Components

Storage Rack Network Components

Cable the ZFS Storage Appliance

ZFS Appliance Power Cord Connection Reference

ZFS Storage Appliance Cabling Reference

Cable IB Switches

Leaf Switch 1 Cabling Reference

Leaf Switch 2 Cabling Reference

IB Switch-to-Switch Cabling Reference

Cable the Ethernet Management Switch

Ethernet Management Switch Cabling Reference

Connect SuperCluster M6-32 to the Facility Networks

Connecting Expansion Racks

Expansion Rack Overview

Expansion Rack Components

Expansion Rack Layouts

Installing Expansion Racks

One Expansion Rack Cabling

Two Expansion Racks Cabling

Three Expansion Racks Cabling

Four Expansion Racks Cabling

Five Expansion Racks Cabling

Six Expansion Racks Cabling

Seven Expansion Racks Cabling

Expansion Rack Default IP Addresses

Understanding Internal Cabling (Expansion Rack)

Oracle ILOM Cabling

Administrative Gigabit Ethernet Port Cabling

Single-Phase PDU Cabling

Three-Phase PDU Cabling (Full Rack)

IB Network Cabling

Glossary

Index

Facility Power Requirements

Electrical work and installations must comply with applicable local, state, or national electrical codes. Contact your facilities manager or qualified electrician to determine what type of power is supplied to the building.

To prevent catastrophic failures, design the input power sources to ensure that adequate power is provided to the PDUs.

In the United States and Canada, ensure that the overall system AC input current load does not exceed 80 percent of the branch circuit AC current rating.

When planning for power distribution requirements, balance the power load between available AC supply branch circuits.

The installation site AC power receptacle must be within 6.6 feet (2 m) of the rack.

Circuit Breaker Requirements

Provide dedicated AC breaker panels for all power circuits that supply power to the storage and expansion racks.

In addition to circuit breakers, provide a stable power source, such as a UPS, to reduce the possibility of component failures. If computer equipment is subjected to repeated power interruptions and fluctuations, then it is susceptible to a higher rate of component failure.

Grounding Guidelines

Electrical circuits must be grounded to the earth.

The storage and expansion racks are shipped with grounding-type power cords. Always connect the cords to grounded power outlets. Because different grounding methods are used, depending on location, check the grounding type. Also refer to documentation, such as IEC documents, for the correct grounding method. Ensure that the facility administrator or qualified electrical engineer verifies the grounding method for the building, and performs the grounding work.

Related Information