Cabling Requirements

Prior to cabling and powering on the server, gather the following network information:

  • Netmask

  • IP address for the SP

  • Gateway IP address

At a minimum, you must connect cables to these ports before powering-on the server for the first time:

  • SP SER MGT port

  • SP NET MGT port (if you plan to use this port as soon as it is available)

  • At least one system on-board Ethernet network port

  • Power cables to the power supply inlet ports