Prepare to Power Off the Switch

Perform this task before powering off the switch.


Note -  The following task lists the basic steps for preparing to power off the switch. For more thorough instructions, refer to Oracle Fabric Manager 5.0.2 Administration Guide and the Oracle Fabric OS 1.0.2 Administration Guide.
  1. Notify affected users that the switch is to be shut down.
  2. Set the priority of the switch to be removed to the lowest.

    Wait for any handover to complete.

  3. Create a backup of the switch configuration for the switch to be removed.

    Refer to Performing Backups in Oracle Fabric Manager 5.0.2 Administration Guide.

  4. Disconnect the power cords at the rear of the switch to power it off.

    See Power Off the Switch.