Return the Modular System to Previous Location

If the modular system was mounted to the floor with concrete anchor bolts, you will need an M12 torque wrench and 10 new M12 concrete anchors and bolts, such as Hilte HSL-3-B M12/25, to reanchor the modular system.

  1. If access to the modular system required moving it, perform the following:
    1. Follow safety precautions.

      Refer to ESD and Safety Precautions in Netra Modular System Installation Guide.

    2. Using two persons, carefully move the modular system to its previous location.
    3. If the system has caster rollers, lock them.
  2. If the modular system was anchored to a concrete floor:
    1. Remove the used anchors and any debris from the concrete holes.

      Note -  You might have to drill holes in other locations if any of the holes do not hold a new anchor securely.
    2. Install the anchors and bolts as follows:

      Caution

      Caution  -  Follow the instructions that come with the manufacturer's anchors and bolts.


      1. Insert 10 anchors through the seismic plate into the holes in the concrete floor.
      2. Using an M12 torque wrench, install and loosely tighten the bolts through the anchors and seismic plate, one in each hole, until all bolts are in.
      3. Tighten each bolt in each anchor approximately 10 in-lbs at a time, until the torque-indicator bolt cap breaks off for each bolt.

        This cap feature is on the Hilte bolts. Other manufacturers might have different methods for confirming proper torque. Carefully follow the manufacturer's instructions to ensure a secure mounting of the bolts.

  3. Continue from Step 6 in Connect and Install Adjacent Components.