SPARC T5-4 Server Installation Guide

Exit Print View

Updated: July 2015
 
 

Install the Server


Caution

Caution  - Do not attempt to move the server alone without a lift. For a one-person installation, all the components must be removed and a lift must be used. For a two-person installation, all the components must be removed and a lift is optional.



Caution

Caution  - There are two rail kits for the SPARC T5-4 server. If you have installed the old rail kit (part number 350-1662-02) without the shipping brace, you cannot ship the server in the rack. If you have installed the new rail kit (part number 7069640) with the shipping braces, there is no restriction on shipping the server in a rack.


  1. Prior to installing the server, confirm that you have removed all of the processor modules, the main module, the power supplies and the fan modules.

    For instructions on how to remove these components, refer to the service manual.

  2. If using a mechanical lift, ensure the lift is level and stable.
  3. Lift the server up to the correct height.
  4. Slide the server into the rack.

    Ensure that the bottom edge of the server has cleared the bottom of the rack rails.


    image:Installing the server with a mechanical lift.
  5. Secure the server to the front panel using four No. 2 Phillips screws.
  6. Replace all of the components that you removed.

    For instructions on how to install these components, refer to the service manual.