Installation Overview

This is a summary of the installation process.

1. Prepare for installation.
Reference
  1. Review the safety precautions, guidelines, site checklists, and site requirements.

  2. Ensure that the site is prepared for the installation.

  3. Complete the worksheets.

Oracle SuperCluster T5-8 Site Checklists and Oracle SuperCluster T5-8 Configuration Worksheets
2. Begin the installation.
  1. Unpack Oracle SuperCluster T5-8.

  2. Place Oracle SuperCluster T5-8 in its allocated space.

  3. Perform preliminary checks before connecting the power cords.

  4. Verify the hardware by visually inspecting the system.

3. Power on the PDUs in the rack.
  1. Connect rack power.

  2. Switch on the six PDU circuit breakers located on the rear of the main PDU (PDU A).

  3. Wait 3 to 5 minutes for power-on self-test device checks to finish and for all Oracle ILOM service processors to boot.

  4. Verify that server standby power is on for each SPARC T5-8 server in Oracle SuperCluster T5-8.

  5. Verify that the main power is on for each database compute mode.

4. The ZFS storage controllers should start up automatically.
If the storage controllers do not start up:
  1. Press the soft switches located on the front of the two ZFS storage controllers.

  2. Wait 3 to 5 minutes for the ZFS storage appliance to initiate NFS services, daemons, and basic services.

  3. Ping the IP address assigned to the ZFS storage controllers to verify whether the system is up and running.

5. Start the Exadata Storage Cells.
Wait for Oracle ILOM to boot, then either press the Power On buttons, or turn on the Exadata Storage Servers through Oracle ILOM.
6. Start the SPARC T5-8 servers.
  1. Press the soft switches located on the front of the SPARC T5-8 servers.

  2. Verify that power is applied to the Ethernet switch.

  3. Verify that power is applied to the Sun Datacenter Infiniband Switch 36 switches.

7. Configure Oracle SuperCluster T5-8.
8. Finish the installation.
(Optional) Install a PCIe card to copy a database from another server.