Review the following facility checklist before installing the server.
Table 13 Access Route and Data Center Room Checklist
|
|
|
|
|
Has the access route been checked for clearances of the packaged equipment?
|
|
|
|
|
Do all the doors and entry ways conform to the width and height requirements for
transportation, including the width of the unpacked unit?
|
|
|
|
|
Are there any ramps, stairs, or thresholds that are in the moving path for the new
hardware?
|
|
|
|
|
Have you confirmed that the access route is free of any obstacles that would expose the device
to shock?
|
|
|
|
|
If there are stairs, then is a loading elevator accessible for moving the equipment?
|
|
|
|
|
Has the rack location been allocated?
|
|
|
|
|
Is there a vacant space in the rack for the new server?
|
|
|
|
|
Does the floor layout meet the equipment maintenance access requirements?
|
|
|
|
|
Is there adequate space available for server maintenance?
|
|
|
|
|
Have cabinet stabilization measures been considered?
|
|
|
|
|
Will the hardware location require any non-standard cable lengths?
|
|
|
|
|
Is the floor to ceiling height a minimum of 2.9 meters (9.6 feet)?
|
|
|
|
|
Is the depth of the raised floor a minimum of 460 mm (18 inches)?
|
|
|
|
|
|