Access Route and Data Center Checklist

Review the following facility requirements before installing the server.

Table 10  Access Route and Data Center Room Checklist
Data Center Room Considerations
Yes
No
N/A
Comment
Has the access route been checked for clearances of the packaged equipment?
Do all the doors and entry ways conform to the width and height requirements for transportation, including the width of the unpacked unit?
Are there any ramps, stairs, or thresholds that are in the moving path for the new hardware?
Have you confirmed that the access route is free of any obstacles that would expose the device to shock?
If there are stairs, then is a loading elevator accessible for moving the equipment?
Has the rack location been allocated?
Is there a vacant space in the rack for the new server?
Does the floor layout meet the equipment maintenance access requirements?
Is there adequate space available for server maintenance?
Have cabinet stabilization measures been considered?
Will the hardware location require any non-standard cable lengths?
Is the floor to ceiling height a minimum of 2914 mm or 2.9 m (9.6 feet)?
Is the depth of the raised floor a minimum of 460 mm (18 inches)?