Install the Battery

  1. Unpack the replacement battery.
  2. Press the new battery into the battery retainer.

    Note -  If disconnected during battery removal, reconnect the auxiliary signal cable to the disk backplane and the SAS cables to the Internal HBA. For more information, see Servicing the Disk Backplane and Servicing SAS Cables.
  3. Return the server to operation.
    1. Install the server top cover.

      See Install the Server Top Cover.

    2. Return the server to the normal rack position.

      See Return the Server to the Normal Rack Position.

    3. Reconnect the power cords to the server power supplies, and power on the server.

      See Reconnect Power and Data Cables and Power On the Server.


      Note -  If the service processor is configured to synchronize with a network time server using the Network Time Protocol (NTP), the Oracle ILOM SP clock is reset as soon as the server is powered on and connected to the network; otherwise, proceed to the next step.
    4. Verify that the System OK LED is lit.
  4. If the service processor is not configured to use NTP, you must do one of the following:
    • Reset the Oracle ILOM SP clock using the Oracle ILOM CLI or the web interface.

      For instructions, refer to the Oracle Integrated Lights Out Manager (ILOM) 4.0 Documentation Library at http://www.oracle.com/goto/ilom/docs.

    • Use the BIOS Setup Utility to reprogram the host clock.

      For the BIOS Main menu that supports this procedure, refer to the Oracle X7 Series Servers Administration Guide at http://www.oracle.com/goto/x86admindiag/docs.