Battery Service Sequence


Note -  You must completely power off the switch before disconnecting the data cables. Similarly, you must attach all data cables before powering on the switch.
Step
Description
Links
1.
Determine if the battery is faulty.
“Determine If the Battery is Faulty” on page 77
2.
Power off both power supplies.
“Power Off a Power Supply” on page 48

Note -  Do not remove the InfiniBand cables until the switch is powered off.

3.
Remove all IB cables.
“Remove an InfiniBand Cable” on page 70
4.
Remove the switch from the rack.
“Remove the Switch From the Rack” on page 79
5.
Replace the battery.
“Replace the Battery” on page 80
6.
Install the switch in the rack.
Switch Installation, installing the switch

Note -  Do not power on the switch.

7.
Install all IB cables.
“Install an InfiniBand Cable” on page 74
8.
Power on both power supplies.
“Power On a Power Supply” on page 53
9.
(Optional) Set the time and date.
Switch Administration, setting the date and time