SPARC T8-4 Server Installation Guide

Exit Print View

Updated: September 2017
 
 

Installing the Server

These topics describe how to install the server into a rack equipped with square mounting holes. If you are installing the server into a rack equipped with round mounting holes, see Determine Correct Rackmount Hardware.


Note -  If the rackmount kit came with its own instructions, use those instructions instead of the instructions in this chapter. After performing the server installation, proceed to Powering On the Server for the First Time for first-time power on.
Step
Description
Links
1.
Ensure that your rack is compatible with the server requirements.
2.
Determine the correct rackmounting hardware and install the hardware.
3.
Install the server in the rack.
4.
(Optional) Install the CMA.
5.
(Optional) If you are installing the server into a rack that will be shipped to another location, install the shipping brace assembly.
6.
Review cabling requirements and port information. Attach data and management cables to the server.
7.
Configure the Oracle ILOM SP and power on the server for the first time.