1. |
Thoroughly clean and vacuum the area
in preparation of the installation. |
|
2. |
Note any problems or peculiarities at
the site that require special equipment. |
|
3. |
Verify that the installation site flooring
has a high enough strength rating to withstand the combined weight
of the rack and any installed equipment. |
|
4. |
Install all necessary electrical equipment
and ensure that sufficient power is provided. |
Refer to the Sun
Rack II Power Distribution Units User's Guide for the
power requirements of the rack PDUs. |
5. |
Ensure that the installation site provides
adequate air conditioning. |
|
6. |
Operate the air conditioning system for
48 hours to bring the room to the appropriate temperature. |
|
7. |
Study the mounting holes and cable routing
floor cutouts for your rack type. |
|
8. |
Study the leveling feet and caster dimensions
for your rack. |
|
9. |
Study the rear cabling space for your
rack. |
|
10. |
Determine the type of top panel for your
rack and study the top cable window dimensions. |
|