Site Preparation Task Overview

Step
Description
Links
1.
Thoroughly clean and vacuum the area in preparation of the installation.
2.
Note any problems or peculiarities at the site that require special equipment.
3.
Verify that the installation site flooring has a high enough strength rating to withstand the combined weight of the rack and any installed equipment.
4.
Install all necessary electrical equipment and ensure that sufficient power is provided.
Refer to the Sun Rack II Power Distribution Units User's Guide for the power requirements of the rack PDUs.
5.
Ensure that the installation site provides adequate air conditioning.
6.
Operate the air conditioning system for 48 hours to bring the room to the appropriate temperature.
7.
Study the mounting holes and cable routing floor cutouts for your rack type.
8.
Study the leveling feet and caster dimensions for your rack.
9.
Study the rear cabling space for your rack.
10.
Determine the type of top panel for your rack and study the top cable window dimensions.