Determine Correct Rackmount Hardware

  • Determine the hardware needed for your rack installation.
    Rack Type
    Fastener Bags Required
    Square hole
    SCREW, SEMS, M6 X 16
    CAGENUTS, M6
    SCREW, FLAT HEAD, M4 X 10
    Round hole (10-32) with corner bezel
    SCREW, SEMS, 10-32 X 10
    SCREW, FLAT HEAD, M4 X 10
    Round hole (M6) with corner bezel
    SCREW, SEMS, M6 X 12
    SCREW, FLAT HEAD, M4 X 10
    Round hole (10-32) inside installation
    SCREW, SHOULDER, 10-32
    SCREW, FLAT HEAD, M4 X 10
    Round hole (M6) inside installation
    SCREW, SEMS, M6 X 12
    SCREW, FLAT HEAD, M4 X 10

    Note -  Some of the fastener bags that are included in the kit are not required to install this server.