Access Route and Data Center Checklist
Review the following facility requirements before installing the server.
|
|
|
|
|
Has the access route been checked for clearances of the
packaged equipment?
|
|
|
|
|
Do all the doors and entry ways conform to the width and
height requirements for transportation, including the width of
the unpacked unit?
|
|
|
|
|
Are there any ramps, stairs, or thresholds that are in the
moving path for the new hardware?
|
|
|
|
|
Have you confirmed that the access route is free of any
obstacles that would expose the device to shock?
|
|
|
|
|
If there are stairs, then is a loading elevator accessible for
moving the equipment?
|
|
|
|
|
Has the rack location been allocated?
|
|
|
|
|
Is there a vacant space in the rack for the new server?
|
|
|
|
|
Does the floor layout meet the equipment maintenance access
requirements?
|
|
|
|
|
Is there adequate space available for server
maintenance?
|
|
|
|
|
Have cabinet stabilization measures been considered?
|
|
|
|
|
Will the hardware location require any non-standard cable
lengths?
|
|
|
|
|
Is the floor to ceiling height a minimum of 2914 mm or 2.9 m
(9.6 feet)?
|
|
|
|
|
|