The server requires five rack units, and should go directly above the unit below it with no gaps.
Studs on the spacers fit into the oval holes on the inside of the back rack rail. Align the bottom of the spacer with the bottom of the system rack space.
The template has rack alignment images on either side; one for the back rack alignment [1], and one for the front rack alignment [2].
Place the cage nuts on the inner-facing side of each rail. There are two cage nuts in each front rail and three cage nuts in each back rail.
To use the cage nut insertion tool, see Use the Cage Nut Insertion Tool.
The rails are labeled left and right, front and back.
The rails have studs and a latch at each end. For each rail:
Do not tighten the screws all the way. Do that later in the procedure: Install the Server Into the Rack.
Next Steps