Connecting an Oracle Exadata Storage Expansion Rack to the SPARC SuperCluster T4-4

Three Sun Datacenter InfiniBand Switch 36 switches are needed when cabling racks together. The SPARC SuperCluster T4-4 and the Oracle Exadata Storage Expansion Half Rack or Oracle Exadata Storage Expansion Full Rack include three Sun Datacenter InfiniBand Switch 36 switches. Two switches are used as leaf switches, and the third switch is used as a spine switch. These switches attach to standard Quad Small Form-factor Pluggable (QSFP) connectors at the end of the InfiniBand cables. The procedures in this section assume the racks are adjacent to each other. If they are not, then longer cables may be required for the connections.


Note -  The Oracle Exadata Storage Expansion Quarter Rack contains only two Sun Datacenter InfiniBand Switch 36 switches (the leaf switches), so no spine switch is available in the Oracle Exadata Storage Expansion Quarter Rack. See Connecting an Oracle Exadata Storage Expansion Quarter Rack to the SPARC SuperCluster T4-4 for more information.

InfiniBand Switch Information for the SPARC SuperCluster T4-4

In the SPARC SuperCluster T4-4, the switch at rack unit 1 (U1) is referred to as the spine switch. The switches at rack unit 18 (U18) and rack unit 24 (U24) are referred to as leaf switches. In a single rack, the two leaf switches are interconnected using seven connections. In addition, each leaf switch has one connection to the spine switch. The leaf switches connect to the spine switch as shown in the following graphic.

image:Graphic showing connections between InfiniBand switches and SPARC                         SuperCluster T4-4 components.

InfiniBand Switch Information for the Oracle Exadata Storage Expansion Rack

In the Oracle Exadata Storage Expansion Rack, the switch at rack unit 1 (U1) is referred to as the spine switch, except for the Oracle Exadata Storage Expansion Quarter Rack which has no spine switch. The switches at rack unit 20 (U20) and rack unit 24 (U24) are referred to as leaf switches.

Connecting an Oracle Exadata Storage Expansion Quarter Rack to the SPARC SuperCluster T4-4

These topics describe how to connect an Oracle Exadata Storage Expansion Quarter Rack to your SPARC SuperCluster T4-4 from Oracle.


Note -  Only one Oracle Exadata Storage Expansion Quarter Rack can be connected to a SPARC SuperCluster T4-4 Half Rack or Full Rack.

Note -  For instructions on connecting an Oracle Exadata Storage Expansion Half Rack or Oracle Exadata Storage Expansion Full Rack to the SPARC SuperCluster T4-4, see Connecting an Oracle Exadata Storage Expansion Half Rack or Oracle Exadata Storage Expansion Full Rack to the SPARC SuperCluster T4-4.

The following graphic shows the cable connections from an Oracle Exadata Storage Expansion Quarter Rack to a SPARC SuperCluster T4-4. The leaf switches within each rack maintain their existing seven connections. The leaf switches interconnect between the racks with two links each using the ports reserved for external connectivity.

image:Graphic showing an expansion quarter rack connected to a SPARC                         SuperCluster Half Rack or Full Rack.

The following graphic shows the cable connections from an Oracle Exadata Storage Expansion Quarter Rack to two or more racks. The following racks can connect to an Oracle Exadata Storage Expansion Quarter Rack:

  • SPARC SuperCluster T4-4 Half Rack

  • SPARC SuperCluster T4-4 Full Rack

  • Oracle Exadata Storage Expansion Half Rack

  • Oracle Exadata Storage Expansion Full Rack

The racks are interconnected using a fat-tree topology. Each leaf switch in the Oracle Exadata Storage Expansion Quarter Rack connects to the spine switches in the other Half Racks or Full Racks with two links each. If there are more than four racks, then use one link instead of two.

image:Graphic showing an expansion quarter rack connected to two or more half                         or full racks.

The following terms are used when referring to the two racks:

  • Rack 1 (R1) refers to the SPARC SuperCluster T4-4

  • Rack 2 (R2) refers to the Oracle Exadata Storage Expansion Quarter Rack

In addition, because the InfiniBand switches are physically located in different rack units in the two racks, the following terms are used when referring to the InfiniBand switches:

  • InfiniBand 1 (IB1) refers to the spine switch, located in U1 in the SPARC SuperCluster T4-4

  • InfiniBand 2 (IB2) refers to the first leaf switch, located in:

    • U18 in the SPARC SuperCluster T4-4

    • U20 in the Oracle Exadata Storage Expansion Rack

  • InfiniBand 3 (IB3) refers to the second leaf switch, located in U24 in both racks

The following table shows the cable connections for a single Oracle Exadata Storage Expansion Quarter Rack to a SPARC SuperCluster T4-4.

Table 89  Leaf Switch Connections for the First Rack in a Two-Rack System
Leaf Switch
Connection
Cable Length
R1-IB3 to Rack 2
R1-IB3-P2A to R2-IB3-P2A
R1-IB3-P2B to R2-IB3-P2B
R1-IB3-P7B to R2-IB2-P7B
R1-IB3-P12A to R2-IB2-P12A
5 meters
R1-IB2 to Rack 2
R1-IB2-P7B to R2-IB3-P7B
R1-IB2-P12A to R2-IB3-P12A
R1-IB2-P2A to R2-IB2-P2A
R1-IB2-P2B to R2-IB2-P2B
5 meters

Connecting an Oracle Exadata Storage Expansion Half Rack or Oracle Exadata Storage Expansion Full Rack to the SPARC SuperCluster T4-4

These topics describe how to connect an Oracle Exadata Storage Expansion Half Rack or Oracle Exadata Storage Expansion Full Rack to your SPARC SuperCluster T4-4 from Oracle.


Note -  For instructions on connecting an Oracle Exadata Storage Expansion Quarter Rack to the SPARC SuperCluster T4-4, see Connecting an Oracle Exadata Storage Expansion Quarter Rack to the SPARC SuperCluster T4-4.

When connecting multiple racks together, remove the seven existing inter-switch connections between each leaf switches, as well as the two connections between the leaf switches and the spine switch. From each leaf switch, distribute eight connections over the spine switches in all racks. In multi-rack environments, the leaf switches inside a rack are no longer directly interconnected, as shown in the following graphic.

image:Graphic showing connections between two racks.

As shown in the preceding graphic, each leaf switch in rack 1 connects to the following switches:

  • Four connections to its internal spine switch

  • Four connections to the spine switch in rack 2

The spine switch in rack 1 connects to the following switches:

  • Eight connections to both internal leaf switches

  • Eight connections to both leaf switches in rack 2

The following terms are used when referring to the two racks:

  • Rack 1 (R1) refers to the SPARC SuperCluster T4-4

  • Rack 2 (R2) refers to the Oracle Exadata Storage Expansion Rack

In addition, because the InfiniBand switches are physically located in different rack units in the two racks, the following terms are used when referring to the InfiniBand switches:

  • InfiniBand 1 (IB1) refers to the spine switch, located in U1 in both racks

  • InfiniBand 2 (IB2) refers to the first leaf switch, located in:

    • U18 in the SPARC SuperCluster T4-4

    • U20 in the Oracle Exadata Storage Expansion Rack

  • InfiniBand 3 (IB3) refers to the second leaf switch, located in U24 in both racks

Two-Rack C20abling

The following table shows the cable connections for the first spine switch (R1-IB1) when cabling two racks together.

Table 90  Leaf Switch Connections for the First Rack in a Two-Rack System
Leaf Switch
Connection
Cable Length
R1-IB3 within Rack 1
R1-IB3-P8A to R1-IB1-P3A
R1-IB3-P8B to R1-IB1-P4A
R1-IB3-P9A to R1-IB1-P5A
R1-IB3-P9B to R1-IB1-P6A
5 meters
R1-IB3 to Rack 2
R1-IB3-P10A to R2-IB1-P7A
R1-IB3-P10B to R2-IB1-P8A
R1-IB3-P11A to R2-IB1-P9A
R1-IB3-P11B to R2-IB1-P10A
5 meters
R1-IB2 within Rack 1
R1-IB2-P8A to R1-IB1-P3B
R1-IB2-P8B to R1-IB1-P4B
R1-IB2-P9A to R1-IB1-P5B
R1-IB2-P9B to R1-IB1-P6B
5 meters
R1-IB2 to Rack 2
R1-IB2-P10A to R2-IB1-P7B
R1-IB2-P10B to R2-IB1-P8B
R1-IB2-P11A to R2-IB1-P9B
R1-IB2-P11B to R2-IB1-P10B
5 meters

The following table shows the cable connections for the second spine switch (R2-IB1) when cabling two racks together.

Table 91  Leaf Switch Connections for the Second Rack in a Two-Rack System
Leaf Switch
Connection
Cable Length
R2-IB3 within Rack 2
R2-IB3-P8A to R2-IB1-P3A
R2-IB3-P8B to R2-IB1-P4A
R2-IB3-P9A to R2-IB1-P5A
R2-IB3-P9B to R2-IB1-P6A
5 meters
R2-IB3 to Rack 1
R2-IB3-P10A to R1-IB1-P7A
R2-IB3-P10B to R1-IB1-P8A
R2-IB3-P11A to R1-IB1-P9A
R2-IB3-P11B to R1-IB1-P10A
5 meters
R2-IB2 within Rack 2
R2-IB2-P8A to R2-IB1-P3B
R2-IB2-P8B to R2-IB1-P4B
R2-IB2-P9A to R2-IB1-P5B
R2-IB2-P9B to R2-IB1-P6B
5 meters
R2-IB2 to Rack 1
R2-IB2-P10A to R1-IB1-P7B
R2-IB2-P10B to R1-IB1-P8B
R2-IB2-P11A to R1-IB1-P9B
R2-IB2-P11B to R1-IB1-P10B
5 meters

Three-Rack Cabling

The following table shows the cable connections for the first spine switch (R1-IB1) when cabling three full racks together.

Table 92  Leaf Switch Connections for the First Rack in a Three-Rack System
Leaf Switch
Connection
Cable Length
R1-IB3 within Rack 1
R1-IB3-P8A to R1-IB1-P3A
R1-IB3-P8B to R1-IB1-P4A
R1-IB3-P9A to R1-IB1-P5A
5 meters
R1-IB3 to Rack 2
R1-IB3-P9B to R2-IB1-P6A
R1-IB3-P10A to R2-IB1-P7A
R1-IB3-P10B to R2-IB1-P8A
5 meters
R1-IB3 to Rack 3
R1-IB3-P11A to R3-IB1-P9A
R1-IB3-P11B to R3-IB1-P10A
5 meters
R1-IB2 within Rack 1
R1-IB2-P8A to R1-IB1-P3B
R1-IB2-P8B to R1-IB1-P4B
R1-IB2-P9A to R1-IB1-P5B
5 meters
R1-IB2 to Rack 2
R1-IB2-P9B to R2-IB1-P6B
R1-IB2-P10A to R2-IB1-P7B
R1-IB2-P10B to R2-IB1-P8B
5 meters
R1-IB2 to Rack 3
R1-IB2-P11A to R3-IB1-P9B
R1-IB2-P11B to R3-IB1-P10B
5 meters

The following table shows the cable connections for the second spine switch (R2-IB1) when cabling three racks together.

Table 93  Leaf Switch Connections for the Second Rack in a Three-Rack System
Leaf Switch
Connection
Cable Length
R2-IB3 within Rack 2
R2-IB3-P8A to R2-IB1-P3A
R2-IB3-P8B to R2-IB1-P4A
R2-IB3-P9A to R2-IB1-P5A
5 meters
R2-IB3 to Rack 1
R2-IB3-P11A to R1-IB1-P9A
R2-IB3-P11B to R1-IB1-P10A
5 meters
R2-IB3 to Rack 3
R2-IB3-P9B to R3-IB1-P6A
R2-IB3-P10A to R3-IB1-P7A
R2-IB3-P10B to R3-IB1-P8A
5 meters
R2-IB2 within Rack 2
R2-IB2-P8A to R2-IB1-P3B
R2-IB2-P8B to R2-IB1-P4B
R2-IB2-P9A to R2-IB1-P5B
5 meters
R2-IB2 to Rack 1
R2-IB2-P11A to R1-IB1-P9B
R2-IB2-P11B to R1-IB1-P10B
5 meters
R2-IB2 to Rack 3
R2-IB2-P9B to R3-IB1-P6B
R2-IB2-P10A to R3-IB1-P7B
R2-IB2-P10B to R3-IB1-P8B
5 meters

The following table shows the cable connections for the third spine switch (R3-IB1) when cabling three full racks together.

Table 94  Leaf Switch Connections for the Third Rack in a Three-Rack System
Leaf Switch
Connection
Cable Length
R3-IB3 within Rack 3
R3-IB3-P8A to R3-IB1-P3A
R3-IB3-P8B to R3-IB1-P4A
R3-IB3-P9A to R3-IB1-P5A
5 meters
R3-IB3 to Rack 1
R3-IB3-P9B to R1-IB1-P6A
R3-IB3-P10A to R1-IB1-P7A
R3-IB3-P10B to R1-IB1-P8A
5 meters
R3-IB3 to Rack 2
R3-IB3-P11A to R2-IB1-P9A
R3-IB3-P11B to R2-IB1-P10A
5 meters
R3-IB2 within Rack 3
R3-IB2-P8A to R3-IB1-P3B
R3-IB2-P8B to R3-IB1-P4B
R3-IB2-P9A to R3-IB1-P5B
5 meters
R3-IB2 to Rack 1
R3-IB2-P9B to R1-IB1-P6B
R3-IB2-P10A to R1-IB1-P7B
R3-IB2-P10B to R1-IB1-P8B
5 meters
R3-IB2 to Rack 2
R3-IB2-P11A to R2-IB1-P9B
R3-IB2-P11B to R2-IB1-P10B
5 meters

Four-Rack Cabling

The following table shows the cable connections for the first spine switch (R1-IB1) when cabling four full racks together.

Table 95  Leaf Switch Connections for the First Rack in a Four-Rack System
Leaf Switch
Connection
Cable Length
R1-IB3 within Rack 1
R1-IB3-P8A to R1-IB1-P3A
R1-IB3-P8B to R1-IB1-P4A
5 meters
R1-IB3 to Rack 2
R1-IB3-P9A to R2-IB1-P5A
R1-IB3-P9B to R2-IB1-P6A
5 meters
R1-IB3 to Rack 3
R1-IB3-P10A to R3-IB1-P7A
R1-IB3-P10B to R3-IB1-P8A
5 meters
R1-IB3 to Rack 4
R1-IB3-P11A to R4-IB1-P9A
R1-IB3-P11B to R4-IB1-P10A
10 meters
R1-IB2 within Rack 1
R1-IB2-P8A to R1-IB1-P3B
R1-IB2-P8B to R1-IB1-P4B
5 meters
R1-IB2 to Rack 2
R1-IB2-P9A to R2-IB1-P5B
R1-IB2-P9B to R2-IB1-P6B
5 meters
R1-IB2 to Rack 3
R1-IB2-P10A to R3-IB1-P7B
R1-IB2-P10B to R3-IB1-P8B
5 meters
R1-IB2 to Rack 4
R1-IB2-P11A to R4-IB1-P9B
R1-IB2-P11B to R4-IB1-P10B
10 meters

The following table shows the cable connections for the second spine switch (R2-IB1) when cabling four full racks together.

Table 96  Leaf Switch Connections for the Second Rack in a Four-Rack System
Leaf Switch
Connection
Cable Length
R2-IB3 within Rack 2
R2-IB3-P8A to R2-IB1-P3A
R2-IB3-P8B to R2-IB1-P4A
5 meters
R2-IB3 to Rack 1
R2-IB3-P11A to R1-IB1-P9A
R2-IB3-P11B to R1-IB1-P10A
5 meters
R2-IB3 to Rack 3
R2-IB3-P9A to R3-IB1-P5A
R2-IB3-P9B to R3-IB1-P6A
5 meters
R2-IB3 to Rack 4
R2-IB3-P10A to R4-IB1-P7A
R2-IB3-P10B to R4-IB1-P8A
5 meters
R2-IB2 within Rack 2
R2-IB2-P8A to R2-IB1-P3B
R2-IB2-P8B to R2-IB1-P4B
5 meters
R2-IB2 to Rack 1
R2-IB2-P11A to R1-IB1-P9B
R2-IB2-P11B to R1-IB1-P10B
5 meters
R2-IB2 to Rack 3
R2-IB2-P9A to R3-IB1-P5B
R2-IB2-P9B to R3-IB1-P6B
5 meters
R2-IB2 to Rack 4
R2-IB2-P10A to R4-IB1-P7B
R2-IB2-P10B to R4-IB1-P8B
5 meters

The following table shows the cable connections for the third spine switch (R3-IB1) when cabling four full racks together.

Table 97  Leaf Switch Connections for the Third Rack in a Four-Rack System
Leaf Switch
Connection
Cable Length
R3-IB3 within Rack 3
R3-IB3-P8A to R3-IB1-P3A
R3-IB3-P8B to R3-IB1-P4A
5 meters
R3-IB3 to Rack 1
R3-IB3-P10A to R1-IB1-P7A
R3-IB3-P10B to R1-IB1-P8A
5 meters
R3-IB3 to Rack 2
R3-IB3-P11A to R2-IB1-P9A
R3-IB3-P11B to R2-IB1-P10A
5 meters
R3-IB3 to Rack 4
R3-IB3-P9A to R4-IB1-P5A
R3-IB3-P9B to R4-IB1-P6A
5 meters
R3-IB2 within Rack 3
R3-IB2-P8A to R3-IB1-P3B
R3-IB2-P8B to R3-IB1-P4B
5 meters
R3-IB2 to Rack 1
R3-IB2-P10A to R1-IB1-P7B
R3-IB2-P10B to R1-IB1-P8B
5 meters
R3-IB2 to Rack 2
R3-IB2-P11A to R2-IB1-P9B
R3-IB2-P11B to R2-IB1-P10B
5 meters
R3-IB2 to Rack 4
R3-IB2-P9A to R4-IB1-P5B
R3-IB2-P9B to R4-IB1-P6B
5 meters

The following table shows the cable connections for the fourth spine switch (R4-IB1) when cabling four full racks together.

Table 98  Leaf Switch Connections for the Fourth Rack in a Four-Rack System
Leaf Switch
Connection
Cable Length
R4-IB3 within Rack 4
R4-IB3-P8A to R4-IB1-P3A
R4-IB3-P8B to R4-IB1-P4A
5 meters
R4-IB3 to Rack 1
R4-IB3-P9A to R1-IB1-P5A
R4-IB3-P9B to R1-IB1-P6A
10 meters
R4-IB3 to Rack 2
R4-IB3-P10A to R2-IB1-P7A
R4-IB3-P10B to R2-IB1-P8A
5 meters
R4-IB3 to Rack 3
R4-IB3-P11A to R3-IB1-P9A
R4-IB3-P11B to R3-IB1-P10A
5 meters
R4-IB2 within Rack 4
R4-IB2-P8A to R4-IB1-P3B
R4-IB2-P8B to R4-IB1-P4B
5 meters
R4-IB2 to Rack 1
R4-IB2-P9A to R1-IB1-P5B
R4-IB2-P9B to R1-IB1-P6B
10 meters
R4-IB2 to Rack 2
R4-IB2-P10A to R2-IB1-P7B
R4-IB2-P10B to R2-IB1-P8B
5 meters
R4-IB2 to Rack 3
R4-IB2-P11A to R3-IB1-P9B
R4-IB2-P11B to R3-IB1-P10B
5 meters

Five-Rack Cabling

The following table shows the cable connections for the first spine switch (R1-IB1) when cabling five full racks together.

Table 99  Leaf Switch Connections for the First Rack in a Five-Rack System
Leaf Switch
Connection
Cable Length
R1 IB3 within Rack 1
R1-IB3-P8A to R1-IB1-P3A
R1-IB3-P8B to R1-IB1-P4A
3 meters
R1 IB3 to Rack 2
R1-IB3-P9A to R2-IB1-P5A
R1-IB3-P9B to R2-IB1-P6A
5 meters
R1 IB3 to Rack 3
R1-IB3-P10A to R3-IB1-P7A
R1-IB3-P10B to R3-IB1-P8A
5 meters
R1 IB3 to Rack 4
R1-IB3-P11A to R4-IB1-P9A
10 meters
R1 IB3 to Rack 5
R1-IB3-P11B to R5-IB1-P10A
10 meters
R1 IB2 within Rack 1
R1-IB2-P8A to R1-IB1-P3B
R1-IB2-P8B to R1-IB1-P4B
3 meters
R1 IB2 to Rack 2
R1-IB2-P9A to R2-IB1-P5B
R1-IB2-P9B to R2-IB1-P6B
3 meters
R1 IB2 to Rack 3
R1-IB2-P10A to R3-IB1-P7B
R1-IB2-P10B to R3-IB1-P8B
5 meters
R1 IB2 to Rack 4
R1-IB2-P11A to R4-IB1-P9B
10 meters
R1 IB2 to Rack 5
R1-IB2-P11B to R5-IB1-P10B
10 meters

The following table shows the cable connections for the second spine switch (R2-IB1) when cabling five full racks together.

Table 100  Leaf Switch Connections for the Second Rack in a Five-Rack System
Leaf Switch
Connection
Cable Length
R2 IB3 within Rack 2
R2-IB3-P8A to R2-IB1-P3A
R2-IB3-P8B to R2-IB1-P4A
3 meters
R2 IB3 to Rack 1
R2-IB3-P11B to R1-IB1-P10A
5 meters
R2 IB3 to Rack 3
R2-IB3-P9A to R3-IB1-P5A
R2-IB3-P9B to R3-IB1-P6A
5 meters
R2 IB3 to Rack 4
R2-IB3-P10A to R4-IB1-P7A
R2-IB3-P10B to R4-IB1-P8A
5 meters
R2 IB3 to Rack 5
R2-IB3-P11A to R5-IB1-P9A
10 meters
R2 IB2 within Rack 2
R2-IB2-P8A to R2-IB1-P3B
R2-IB2-P8B to R2-IB1-P4B
3 meters
R2 IB2 to Rack 1
R2-IB2-P11B to R1-IB1-P10B
5 meters
R2 IB2 to Rack 3
R2-IB2-P9A to R3-IB1-P5B
R2-IB2-P9B to R3-IB1-P6B
5 meters
R2 IB2 to Rack 4
R2-IB2-P10A to R4-IB1-P7B
R2-IB2-P10B to R4-IB1-P8B
5 meters
R2 IB2 to Rack 5
R2-IB2-P11A to R5-IB1-P9B
10 meters

The following table shows the cable connections for the third spine switch (R3-IB1) when cabling five full racks together.

Table 101  Leaf Switch Connections for the Third Rack in a Five-Rack System
Leaf Switch
Connection
Cable Length
R3 IB3 within Rack 3
R3-IB3-P8A to R3-IB1-P3A
R3-IB3-P8B to R3-IB1-P4A
3 meters
R3 IB3 to Rack 1
R3-IB3-P11A to R1-IB1-P9A
5 meters
R3 IB3 to Rack 2
R3-IB3-P11B to R2-IB1-P10A
5 meters
R3 IB3 to Rack 4
R3-IB3-P9A to R4-IB1-P5A
R3-IB3-P9B to R4-IB1-P6A
5 meters
R3 IB3 to Rack 5
R3-IB3-P10A to R5-IB1-P7A
R3-IB3-P10B to R5-IB1-P8A
5 meters
R3 IB2 within Rack 3
R3-IB2-P8A to R3-IB1-P3B
R3-IB2-P8B to R3-IB1-P4B
3 meters
R3 IB2 to Rack 1
R3-IB2-P11A to R1-IB1-P9B
5 meters
R3 IB2 to Rack 2
R3-IB2-P11B to R2-IB1-P10B
5 meters
R3 IB2 to Rack 4
R3-IB2-P9A to R4-IB1-P5B
R3-IB2-P9B to R4-IB1-P6B
5 meters
R3 IB2 to Rack 5
R3-IB2-P10A to R5-IB1-P7B
R3-IB2-P10B to R5-IB1-P8B
5 meters

The following table shows the cable connections for the fourth spine switch (R4-IB1) when cabling five full racks together.

Table 102  Leaf Switch Connections for the Fourth Rack in a Five-Rack System
Leaf Switch
Connection
Cable Length
R4 IB3 within Rack 4
R4-IB3-P8A to R4-IB1-P3A
R4-IB3-P8B to R4-IB1-P4A
3 meters
R4 IB3 to Rack 1
R4-IB3-P10A to R1-IB1-P7A
R4-IB3-P10B to R1-IB1-P8A
10 meters
R4 IB3 to Rack 2
R4-IB3-P11A to R2-IB1-P9A
5 meters
R4 IB3 to Rack 3
R4-IB3-P11B to R3-IB1-P10A
5 meters
R4 IB3 to Rack 5
R4-IB3-P9A to R5-IB1-P5A
R4-IB3-P9B to R5-IB1-P6A
5 meters
R4 IB2 within Rack 4
R4-IB2-P8A to R4-IB1-P3B
R4-IB2-P8B to R4-IB1-P4B
3 meters
R4 IB2 to Rack 1
R4-IB2-P10A to R1-IB1-P7B
R4-IB2-P10B to R1-IB1-P8B
10 meters
R4 IB2 to Rack 2
R4-IB2-P11A to R2-IB1-P9B
5 meters
R4 IB2 to Rack 3
R4-IB2-P11B to R3-IB1-P10B
5 meters
R4 IB2 to Rack 5
R4-IB2-P9A to R5-IB1-P5B
R4-IB2-P9B to R5-IB1-P6B
5 meters

The following table shows the cable connections for the fifth spine switch (R5-IB1) when cabling five full racks together.

Table 103  Leaf Switch Connections for the Fifth Rack in a Five-Rack System
Leaf Switch
Connection
Cable Length
R5 IB3 within Rack 5
R5-IB3-P8A to R5-IB1-P3A
R5-IB3-P8B to R5-IB1-P4A
3 meters
R5 IB3 to Rack 1
R5-IB3-P9A to R1-IB1-P5A
R5-IB3-P9B to R1-IB1-P6A
10 meters
R5 IB3 to Rack 2
R5-IB3-P10A to R2-IB1-P7A
R5-IB3-P10B to R2-IB1-P8A
10 meters
R5 IB3 to Rack 3
R5-IB3-P11A to R3-IB1-P9A
5 meters
R5 IB3 to Rack 4
R5-IB3-P11B to R4-IB1-P10A
5 meters
R5 IB2 within Rack 5
R5-IB2-P8A to R5-IB1-P3B
R5-IB2-P8B to R5-IB1-P4B
3 meters
R5 IB2 to Rack 1
R5-IB2-P9A to R1-IB1-P5B
R5-IB2-P9B to R1-IB1-P6B
10 meters
R5 IB2 to Rack 2
R5-IB2-P10A to R2-IB1-P7B
R5-IB3-P10B to R2-IB1-P8B
10 meters
R5 IB2 to Rack 3
R5-IB2-P11A to R3-IB1-P9B
5 meters
R5 IB2 to Rack 4
R5-IB2-P11B to R4-IB1-P10B
5 meters

Six-Rack Cabling

The following table shows the cable connections for the first spine switch (R1-IB1) when cabling six full racks together.

Table 104  Leaf Switch Connections for the First Rack in a Six-Rack System
Leaf Switch
Connection
Cable Length
R1 IB3 within Rack 1
R1-IB3-P8A to R1-IB1-P3A
R1-IB3-P8B to R1-IB1-P4A
3 meters
R1 IB3 to Rack 2
R1-IB3-P9A to R2-IB1-P5A
R1-IB3-P9B to R2-IB1-P6A
5 meters
R1 IB3 to Rack 3
R1-IB3-P10A to R3-IB1-P7A
5 meters
R1 IB3 to Rack 4
R1-IB3-P10B to R4-IB1-P8A
10 meters
R1 IB3 to Rack 5
R1-IB3-P11A to R5-IB1-P9A
10 meters
R1 IB3 to Rack 6
R1-IB3-P11B to R6-IB1-P10A
10 meters
R1 IB2 within Rack 1
R1-IB2-P8A to R1-IB1-P3B
R1-IB2-P8B to R1-IB1-P4B
3 meters
R1 IB2 to Rack 2
R1-IB2-P9A to R2-IB1-P5B
R1-IB2-P9B to R2-IB1-P6B
5 meters
R1 IB2 to Rack 3
R1-IB2-P10A to R3-IB1-P7B
5 meters
R1 IB2 to Rack 4
R1-IB2-P10B to R4-IB1-P8B
10 meters
R1 IB2 to Rack 5
R1-IB2-P11A to R5-IB1-P9B
10 meters
R1 IB2 to Rack 6
R1-IB2-P11B to R6-IB1-P10B
10 meters

The following table shows the cable connections for the second spine switch (R2-IB1) when cabling six full racks together.

Table 105  Leaf Switch Connections for the Second Rack in a Six-Rack System
Leaf Switch
Connection
Cable Length
R2 IB3 within Rack 2
R2-IB3-P8A to R2-IB1-P3A
R2-IB3-P8B to R2-IB1-P4A
3 meters
R2 IB3 to Rack 1
R2-IB3-P11B to R1-IB1-P10A
5 meters
R2 IB3 to Rack 3
R2-IB3-P9A to R3-IB1-P5A
R2-IB3-P9B to R3-IB1-P6A
5 meters
R2 IB3 to Rack 4
R2-IB3-P10A to R4-IB1-P7A
5 meters
R2 IB3 to Rack 5
R2-IB3-P10B to R5-IB1-P8A
10 meters
R2 IB3 to Rack 6
R2-IB3-P11Ato R6-IB1-P9A
10 meters
R2 IB2 within Rack 2
R2-IB2-P8A to R2-IB1-P3B
R2-IB2-P8B to R2-IB1-P4B
3 meters
R2 IB2 to Rack 1
R2-IB2-P11B to R1-IB1-P10B
5 meters
R2 IB2 to Rack 3
R2-IB2-P9A to R3-IB1-P5B
R2-IB2-P9B to R3-IB1-P6B
5 meters
R2 IB2 to Rack 4
R2-IB2-P10A to R4-IB1-P7B
5 meters
R2 IB2 to Rack 5
R2-IB2-P10B to R5-IB1-P8B
10 meters
R2 IB2 to Rack 6
R2-IB2-P11Ato R6-IB1-P9B
10 meters

The following table shows the cable connections for the third spine switch (R3-IB1) when cabling six full racks together.

Table 106  Leaf Switch Connections for the Third Rack in a Six-Rack System
Leaf Switch
Connection
Cable Length
R3 IB3 within Rack 3
R3-IB3-P8A to R3-IB1-P3A
R3-IB3-P8B to R3-IB1-P4A
3 meters
R3 IB3 to Rack 1
R3-IB3-P11A to R1-IB1-P9A
5 meters
R3 IB3 to Rack 2
R3-IB3-P11B to R2-IB1-P10A
5 meters
R3 IB3 to Rack 4
R3-IB3-P9A to R4-IB1-P5A
R3-IB3-P9B to R4-IB1-P6A
5 meters
R3 IB3 to Rack 5
R3-IB3-P10A to R5-IB1-P7A
5 meters
R3 IB3 to Rack 6
R3-IB3-P10B to R6-IB1-P8A
5 meters
R3 IB2 within Rack 3
R3-IB2-P8A to R3-IB1-P3B
R3-IB2-P8B to R3-IB1-P4B
3 meters
R3 IB2 to Rack 1
R3-IB2-P11A to R1-IB1-P9B
5 meters
R3 IB2 to Rack 2
R3-IB2-P11B to R2-IB1-P10B
5 meters
R3 IB2 to Rack 4
R3-IB2-P9A to R4-IB1-P5B
R3-IB2-P9B to R4-IB1-P6B
5 meters
R3 IB2 to Rack 5
R3-IB2-P10A to R5-IB1-P7B
5 meters
R3 IB2 to Rack 6
R3-IB2-P10B to R6-IB1-P8B
5 meters

The following table shows the cable connections for the fourth spine switch (R4-IB1) when cabling six full racks together.

Table 107  Leaf Switch Connections for the Fourth Rack in a Six-Rack System
Leaf Switch
Connection
Cable Length
R4 IB3 within Rack 4
R4-IB3-P8A to R4-IB1-P3A
R4-IB3-P8B to R4-IB1-P4A
3 meters
R4 IB3 to Rack 1
R4-IB3-P10B to R1-IB1-P8A
10 meters
R4 IB3 to Rack 2
R4-IB3-P11A to R2-IB1-P9A
5 meters
R4 IB3 to Rack 3
R4-IB3-P11B to R3-IB1-P10A
5 meters
R4 IB3 to Rack 5
R4-IB3-P9A to R5-IB1-P5A
R4-IB3-P9B to R5-IB1-P6A
5 meters
R4 IB3 to Rack 6
R4-IB3-P10A to R6-IB1-P7A
5 meters
R4 IB2 within Rack 4
R4-IB2-P8A to R4-IB1-P3B
R4-IB2-P8B to R4-IB1-P4B
3 meters
R4 IB2 to Rack 1
R4-IB2-P10B to R1-IB1-P8B
10 meters
R4 IB2 to Rack 2
R4-IB2-P11A to R2-IB1-P9B
5 meters
R4 IB2 to Rack 3
R4-IB2-P11B to R3-IB1-P10B
5 meters
R4 IB2 to Rack 5
R4-IB2-P9A to R5-IB1-P5B
R4-IB2-P9B to R5-IB1-P6B
5 meters
R4 IB2 to Rack 6
R4-IB2-P10A to R6-IB1-P7B
5 meters

The following table shows the cable connections for the fifth spine switch (R5-IB1) when cabling six full racks together.

Table 108  Leaf Switch Connections for the Fifth Rack in a Six-Rack System
Leaf Switch
Connection
Cable Length
R5 IB3 within Rack 5
R5-IB3-P8A to R5-IB1-P3A
R5-IB3-P8B to R5-IB1-P4A
3 meters
R5 IB3 to Rack 1
R5-IB3-P10A to R1-IB1-P7A
10 meters
R5 IB3 to Rack 2
R5-IB3-P10B to R2-IB1-P8A
10 meters
R5 IB3 to Rack 3
R5-IB3-P11A to R3-IB1-P9A
5 meters
R5 IB3 to Rack 4
R5-IB3-P11B to R4-IB1-P10A
5 meters
R5 IB3 to Rack 6
R5-IB3-P9A to R6-IB1-P5A
R5-IB3-P9B to R6-IB1-P6A
5 meters
R5 IB2 within Rack 5
R5-IB2-P8A to R5-IB1-P3B
R5-IB2-P8B to R5-IB1-P4B
3 meters
R5 IB2 to Rack 1
R5-IB2-P10A to R1-IB1-P7B
10 meters
R5 IB2 to Rack 2
R5-IB3-P10B to R2-IB1-P8B
10 meters
R5 IB2 to Rack 3
R5-IB2-P11A to R3-IB1-P9B
5 meters
R5 IB2 to Rack 4
R5-IB2-P11B to R4-IB1-P10B
5 meters
R5 IB2 to Rack 6
R5-IB2-P9A to R6-IB1-P5B
R5-IB2-P9B to R6-IB1-P6B
5 meters

The following table shows the cable connections for the sixth spine switch (R6-IB1) when cabling six full racks together.

Table 109  Leaf Switch Connections for the Sixth Rack in a Six-Rack System
Leaf Switch
Connection
Cable Length
R6 IB3 within Rack 6
R6-IB3-P8A to R6-IB1-P3A
R6-IB3-P8B to R6-IB1-P4A
3 meters
R6 IB3 to Rack 1
R6-IB3-P9A to R1-IB1-P5A
R6-IB3-P9B to R1-IB1-P6A
10 meters
R6 IB3 to Rack 2
R6-IB3-P10A to R2-IB1-P7A
10 meters
R6 IB3 to Rack 3
R6-IB3-P10B to R3-IB1-P8A
5 meters
R6 IB3 to Rack 4
R6-IB3-P11A to R4-IB1-P9A
5 meters
R6 IB3 to Rack 5
R6-IB3-P11B to R5-IB1-P10A
5 meters
R6 IB2 within Rack 6
R6-IB2-P8A to R6-IB1-P3B
R6-IB2-P8B to R6-IB1-P4B
3 meters
R6 IB2 to Rack 2
R6-IB3-P10A to R2-IB1-P7B
10 meters
R6 IB2 to Rack 1
R6-IB2-P9A to R1-IB1-P5B
R6-IB2-P9B to R1-IB1-P6B
10 meters
R6 IB2 to Rack 3
R6-IB2-P10B to R3-IB1-P8B
5 meters
R6 IB2 to Rack 4
R6-IB2-P11A to R4-IB1-P9B
5 meters
R6 IB2 to Rack 5
R6-IB2-P11B to R5-IB1-P10B
5 meters

Seven-Rack Cabling

The following table shows the cable connections for the first spine switch (R1-IB1) when cabling seven full racks together.

Table 110  Leaf Switch Connections for the First Rack in a Seven-Rack System
Leaf Switch
Connection
Cable Length
R1 IB3 within Rack 1
R1-IB3-P8A to R1-IB1-P3A
R1-IB3-P8B to R1-IB1-P4A
3 meters
R1 IB3 to Rack 2
R1-IB3-P9A to R2-IB1-P5A
5 meters
R1 IB3 to Rack 3
R1-IB3-P9B to R3-IB1-P6A
5 meters
R1 IB3 to Rack 4
R1-IB3-P10A to R4-IB1-P7A
10 meters
R1 IB3 to Rack 5
R1-IB3-P10B to R5-IB1-P8A
10 meters
R1 IB3 to Rack 6
R1-IB3-P11A to R6-IB1-P9A
10 meters
R1 IB3 to Rack 7
R1-IB3-P11B to R7-IB1-P10A
10 meters
R1 IB2 within Rack 1
R1-IB2-P8A to R1-IB1-P3B
R1-IB2-P8B to R1-IB1-P4B
3 meters
R1 IB2 to Rack 2
R1-IB2-P9A to R2-IB1-P5B
5 meters
R1 IB2 to Rack 3
R1-IB2-P9B to R3-IB1-P6B
5 meters
R1 IB2 to Rack 4
R1-IB2-P10A to R4-IB1-P7B
10 meters
R1 IB2 to Rack 5
R1-IB2-P10B to R5-IB1-P8B
10 meters
R1 IB2 to Rack 6
R1-IB2-P11A to R6-IB1-P9B
10 meters
R1 IB2 to Rack 7
R1-IB2-P11B to R7-IB1-P10B
10 meters

The following table shows the cable connections for the second spine switch (R2-IB1) when cabling seven full racks together.

Table 111  Leaf Switch Connections for the Second Rack in a Seven-Rack System
Leaf Switch
Connection
Cable Length
R2 IB3 within Rack 2
R2-IB3-P8A to R2-IB1-P3A
R2-IB3-P8B to R2-IB1-P4A
3 meters
R2 IB3 to Rack 1
R2-IB3-P11B to R1-IB1-P10A
5 meters
R2 IB3 to Rack 3
R2-IB3-P9A to R3-IB1-P5A
5 meters
R2 IB3 to Rack 4
R2-IB3-P9B to R4-IB1-P6A
5 meters
R2 IB3 to Rack 5
R2-IB3-P10A to R5-IB1-P7A
10 meters
R2 IB3 to Rack 6
R2-IB3-P10B to R6-IB1-P8A
10 meters
R2 IB3 to Rack 7
R2-IB3-P11A to R7-IB1-P9A
10 meters
R2 IB2 within Rack 2
R2-IB2-P8A to R2-IB1-P3B
R2-IB2-P8B to R2-IB1-P4B
3 meters
R2 IB2 to Rack 1
R2-IB2-P11B to R1-IB1-P10B
5 meters
R2 IB2 to Rack 3
R2-IB2-P9A to R3-IB1-P5B
5 meters
R2 IB2 to Rack 4
R2-IB2-P9B to R4-IB1-P6B
5 meters
R2 IB2 to Rack 5
R2-IB2-P10A to R5-IB1-P7B
10 meters
R2 IB2 to Rack 6
R2-IB2-P10Bto R6-IB1-P8B
10 meters
R2 IB2 to Rack 7
R2-IB2-P11A to R7-IB1-P9B
10 meters

The following table shows the cable connections for the third spine switch (R3-IB1) when cabling seven full racks together.

Table 112  Leaf Switch Connections for the Third Rack in a Seven-Rack System
Leaf Switch
Connection
Cable Length
R3 IB3 within Rack 3
R3-IB3-P8A to R3-IB1-P3A
R3-IB3-P8B to R3-IB1-P4A
3 meters
R3 IB3 to Rack 1
R3-IB3-P11A to R1-IB1-P9A
5 meters
R3 IB3 to Rack 2
R3-IB3-P11B to R2-IB1-P10A
5 meters
R3 IB3 to Rack 4
R3-IB3-P9A to R4-IB1-P5A
5 meters
R3 IB3 to Rack 5
R3-IB3-P9B to R5-IB1-P6A
5 meters
R3 IB3 to Rack 6
R3-IB3-P10A to R6-IB1-P7A
10 meters
R3 IB3 to Rack 7
R3-IB3-P10B to R7-IB1-P8A
10 meters
R3 IB2 within Rack 3
R3-IB2-P8A to R3-IB1-P3B
R3-IB2-P8B to R3-IB1-P4B
3 meters
R3 IB2 to Rack 1
R3-IB2-P11A to R1-IB1-P9B
5 meters
R3 IB2 to Rack 2
R3-IB2-P11B to R2-IB1-P10B
5 meters
R3 IB2 to Rack 4
R3-IB2-P9A to R4-IB1-P5B
5 meters
R3 IB2 to Rack 5
R3-IB2-P9B to R5-IB1-P6B
5 meters
R3 IB2 to Rack 6
R3-IB2-P10A to R6-IB1-P7B
10 meters
R3 IB2 to Rack 7
R3-IB2-P10B to R7-IB1-P8B
10 meters

The following table shows the cable connections for the fourth spine switch (R4-IB1) when cabling seven full racks together.

Table 113  Leaf Switch Connections for the Fourth Rack in a Seven-Rack System
Leaf Switch
Connection
Cable Length
R4 IB3 within Rack 4
R4-IB3-P8A to R4-IB1-P3A
R4-IB3-P8B to R4-IB1-P4A
3 meters
R4 IB3 to Rack 1
R4-IB3-P10B to R1-IB1-P8A
10 meters
R4 IB3 to Rack 2
R4-IB3-P11A to R2-IB1-P9A
5 meters
R4 IB3 to Rack 3
R4-IB3-P11B to R3-IB1-P10A
5 meters
R4 IB3 to Rack 5
R4-IB3-P9A to R5-IB1-P5A
5 meters
R4 IB3 to Rack 6
R4-IB3-P9B to R6-IB1-P6A
5 meters
R4 IB3 to Rack 7
R4-IB3-P10A to R7-IB1-P7A
10 meters
R4 IB2 within Rack 4
R4-IB2-P8A to R4-IB1-P3B
R4-IB2-P8B to R4-IB1-P4B
3 meters
R4 IB2 to Rack 1
R4-IB2-P10B to R1-IB1-P8B
10 meters
R4 IB2 to Rack 2
R4-IB2-P11A to R2-IB1-P9B
5 meters
R4 IB2 to Rack 3
R4-IB2-P11B to R3-IB1-P10B
5 meters
R4 IB2 to Rack 5
R4-IB2-P9A to R5-IB1-P5B
5 meters
R4 IB2 to Rack 6
R4-IB2-P9B to R6-IB1-P6B
5 meters
R4 IB2 to Rack 7
R4-IB2-P10A to R7-IB1-P7B
10 meters

The following table shows the cable connections for the fifth spine switch (R5-IB1) when cabling seven full racks together.

Table 114  Leaf Switch Connections for the Fifth Rack in a Seven-Rack System
Leaf Switch
Connection
Cable Length
R5 IB3 within Rack 5
R5-IB3-P8A to R5-IB1-P3A
R5-IB3-P8B to R5-IB1-P4A
3 meters
R5 IB3 to Rack 1
R5-IB3-P10A to R1-IB1-P7A
10 meters
R5 IB3 to Rack 2
R5-IB3-P10B to R2-IB1-P8A
10 meters
R5 IB3 to Rack 3
R5-IB3-P11A to R3-IB1-P9A
5 meters
R5 IB3 to Rack 4
R5-IB3-P11B to R4-IB1-P10A
5 meters
R5 IB3 to Rack 6
R5-IB3-P9A to R6-IB1-P5A
5 meters
R5 IB3 to Rack 7
R5-IB3-P9B to R7-IB1-P6A
5 meters
R5 IB2 within Rack 5
R5-IB2-P8A to R5-IB1-P3B
R5-IB2-P8B to R5-IB1-P4B
3 meters
R5 IB2 to Rack 1
R5-IB2-P10A to R1-IB1-P7B
10 meters
R5 IB2 to Rack 2
R5-IB3-P10B to R2-IB1-P8B
10 meters
R5 IB2 to Rack 3
R5-IB2-P11A to R3-IB1-P9B
5 meters
R5 IB2 to Rack 4
R5-IB2-P11B to R4-IB1-P10B
5 meters
R5 IB2 to Rack 6
R5-IB2-P9A to R6-IB1-P5B
5 meters
R5 IB2 to Rack 7
R5-IB2-P9B to R7-IB1-P6B
5 meters

The following table shows the cable connections for the sixth spine switch (R6-IB1) when cabling seven full racks together.

Table 115  Leaf Switch Connections for the Sixth Rack in a Seven-Rack System
Leaf Switch
Connection
Cable Length
R6 IB3 within Rack 6
R6-IB3-P8A to R6-IB1-P3A
R6-IB3-P8B to R6-IB1-P4A
3 meters
R6 IB3 to Rack 1
R6-IB3-P9B to R1-IB1-P6A
10 meters
R6 IB3 to Rack 2
R6-IB3-P10A to R2-IB1-P7A
10 meters
R6 IB3 to Rack 3
R6-IB3-P10B to R3-IB1-P8A
5 meters
R6 IB3 to Rack 4
R6-IB3-P11A to R4-IB1-P9A
5 meters
R6 IB3 to Rack 5
R6-IB3-P11B to R5-IB1-P10A
5 meters
R6 IB3 to Rack 7
R6-IB3-P9A to R7-IB1-P5A
5 meters
R6 IB2 within Rack 6
R6-IB2-P8A to R6-IB1-P3B
R6-IB2-P8B to R6-IB1-P4B
3 meters
R6 IB2 to Rack 1
R6-IB2-P9B to R1-IB1-P6B
10 meters
R6 IB2 to Rack 2
R6-IB3-P10A to R2-IB1-P7B
10 meters
R6 IB2 to Rack 3
R6-IB2-P10B to R3-IB1-P8B
5 meters
R6 IB2 to Rack 4
R6-IB2-P11A to R4-IB1-P9B
5 meters
R6 IB2 to Rack 5
R6-IB2-P11B to R5-IB1-P10B
5 meters
R6 IB2 to Rack 7
R6-IB3-P9A to R7-IB1-P5B
5 meters

The following table shows the cable connections for the seventh spine switch (R7-IB1) when cabling seven full racks together.

Table 116  Leaf Switch Connections for the Seventh Rack in a Seven-Rack System
Leaf Switch
Connection
Cable Length
R7 IB3 within Rack 7
R7-IB3-P8A to R7-IB1-P3A
R7-IB3-P8B to R7-IB1-P4A
3 meters
R7 IB3 to Rack 1
R7-IB3-P9A to R1-IB1-P5A
10 meters
R7 IB3 to Rack 2
R7-IB3-P9B to R2-IB1-P6A
10 meters
R7 IB3 to Rack 3
R7-IB3-P10A to R3-IB1-P7A
10 meters
R7 IB3 to Rack 4
R7-IB3-P10B to R4-IB1-P8A
10 meters
R7 IB3 to Rack 5
R7-IB3-P11A to R5-IB1-P9A
5 meters
R7 IB3 to Rack 6
R7-IB3-P11B to R6-IB1-P10A
5 meters
R7 IB2 within Rack 7
R7-IB2-P8A to R7-IB1-P3B
R7-IB2-P8B to R7-IB1-P4B
3 meters
R7 IB2 to Rack 1
R7-IB2-P9A to R1-IB1-P5B
10 meters
R7 IB2 to Rack 2
R7-IB3-P9B to R2-IB1-P6B
10 meters
R7 IB2 to Rack 3
R7-IB2-P10A to R3-IB1-P7B
10 meters
R7 IB2 to Rack 4
R7-IB2-P10B to R4-IB1-P8B
10 meters
R7 IB2 to Rack 5
R7-IB2-P11A to R5-IB1-P9B
5 meters
R7 IB2 to Rack 6
R7-IB3-P11B to R6-IB1-P10B
5 meters

Eight-Rack Cabling

The following table shows the cable connections for the first spine switch (R1-IB1) when cabling eight full racks together.

Table 117  Leaf Switch Connections for the First Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R1 IB3 within Rack 1
R1-IB3-P8A to R1-IB1-P3A
3 meters
R1 IB3 to Rack 2
R1-IB3-P8B to R2-IB1-P4A
5 meters
R1 IB3 to Rack 3
R1-IB3-P9A to R3-IB1-P5A
5 meters
R1 IB3 to Rack 4
R1-IB3-P9B to R4-IB1-P6A
10 meters
R1 IB3 to Rack 5
R1-IB3-P10A to R5-IB1-P7A
10 meters
R1 IB3 to Rack 6
R1-IB3-P10B to R6-IB1-P8A
10 meters
R1 IB3 to Rack 7
R1-IB3-P11A to R7-IB1-P9A
10 meters
R1 IB3 to Rack 8
R1-IB3-P11B to R8-IB1-P10A
10 meters
R1 IB2 within Rack 1
R1-IB2-P8A to R1-IB1-P3B
3 meters
R1 IB2 to Rack 2
R1-IB2-P8B to R2-IB1-P4B
5 meters
R1 IB2 to Rack 3
R1-IB2-P9A to R3-IB1-P5B
5 meters
R1 IB2 to Rack 4
R1-IB2-P9B to R4-IB1-P6B
10 meters
R1 IB2 to Rack 5
R1-IB2-P10A to R5-IB1-P7B
10 meters
R1 IB2 to Rack 6
R1-IB2-P10B to R6-IB1-P8B
10 meters
R1 IB2 to Rack 7
R1-IB2-P11A to R7-IB1-P8B
10 meters
R1 IB2 to Rack 8
R1-IB2-P11B to R8-IB1-P10B
10 meters

The following table shows the cable connections for the second spine switch (R2-IB1) when cabling eight full racks together.

Table 118  Leaf Switch Connections for the Second Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R2 IB3 within Rack 2
R2-IB3-P8A to R2-IB1-P3A
3 meters
R2 IB3 to Rack 1
R2-IB3-P11B to R1-IB1-P10A
5 meters
R2 IB3 to Rack 3
R2-IB3-P8B to R3-IB1-P4A
5 meters
R2 IB3 to Rack 4
R2-IB3-P9A to R4-IB1-P5A
5 meters
R2 IB3 to Rack 5
R2-IB3-P9B to R5-IB1-P6A
10 meters
R2 IB3 to Rack 6
R2-IB3-P10A to R6-IB1-P7A
10 meters
R2 IB3 to Rack 7
R2-IB3-P10B to R7-IB1-P8A
10 meters
R2 IB3 to Rack 8
R2-IB3-P11A to R8-IB1-P9A
10 meters
R2 IB2 within Rack 2
R2-IB2-P8A to R2-IB1-P3B
3 meters
R2 IB2 to Rack 1
R2-IB2-P11B to R1-IB1-P10B
5 meters
R2 IB2 to Rack 3
R2-IB2-P8B to R3-IB1-P4B
5 meters
R2 IB2 to Rack 4
R2-IB2-P9A to R4-IB1-P5B
5 meters
R2 IB2 to Rack 5
R2-IB2-P9B to R5-IB1-P6B
10 meters
R2 IB2 to Rack 6
R2-IB2-P10A to R6-IB1-P7B
10 meters
R2 IB2 to Rack 7
R2-IB2-P10B to R7-IB1-P8B
10 meters
R2 IB2 to Rack 8
R2-IB2-P11A to R8-IB1-P9B
10 meters

The following table shows the cable connections for the third spine switch (R3-IB1) when cabling eight full racks together.

Table 119  Leaf Switch Connections for the Third Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R3 IB3 within Rack 3
R3-IB3-P8A to R3-IB1-P3A
3 meters
R3 IB3 to Rack 1
R3-IB3-P11A to R1-IB1-P9A
5 meters
R3 IB3 to Rack 2
R3-IB3-P11B to R2-IB1-P10A
5 meters
R3 IB3 to Rack 4
R3-IB3-P8B to R4-IB1-P4A
5 meters
R3 IB3 to Rack 5
R3-IB3-P9A to R5-IB1-P5A
5 meters
R3 IB3 to Rack 6
R3-IB3-P9B to R6-IB1-P6A
5 meters
R3 IB3 to Rack 7
R3-IB3-P10A to R7-IB1-P7A
10 meters
R3 IB3 to Rack 8
R3-IB3-P10B to R8-IB1-P8A
10 meters
R3 IB2 within Rack 3
R3-IB2-P8A to R3-IB1-P3B
3 meters
R3 IB2 to Rack 1
R3-IB2-P11A to R1-IB1-P9B
5 meters
R3 IB2 to Rack 2
R3-IB2-P11B to R2-IB1-P10B
5 meters
R3 IB2 to Rack 4
R3-IB2-P8B to R4-IB1-P4B
5 meters
R3 IB2 to Rack 5
R3-IB2-P9A to R5-IB1-P5B
5 meters
R3 IB2 to Rack 6
R3-IB2-P9B to R6-IB1-P6B
5 meters
R3 IB2 to Rack 7
R3-IB2-P10A to R7-IB1-P7B
10 meters
R3 IB2 to Rack 8
R3-IB2-P10B to R8-IB1-P8B
10 meters

The following table shows the cable connections for the fourth spine switch (R4-IB1) when cabling eight full racks together.

Table 120  Leaf Switch Connections for the Fourth Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R4 IB3 within Rack 4
R4-IB3-P8A to R4-IB1-P3A
3 meters
R4 IB3 to Rack 1
R4-IB3-P10B to R1-IB1-P8A
10 meters
R4 IB3 to Rack 2
R4-IB3-P11A to R2-IB1-P9A
5 meters
R4 IB3 to Rack 3
R4-IB3-P11B to R3-IB1-P10A
5 meters
R4 IB3 to Rack 5
R4-IB3-P8B to R5-IB1-P4A
5 meters
R4 IB3 to Rack 6
R4-IB3-P9A to R6-IB1-P5A
5 meters
R4 IB3 to Rack 7
R4-IB3-P9B to R7-IB1-P6A
10 meters
R4 IB3 to Rack 8
R4-IB3-P10A to R8-IB1-P7A
10 meters
R4 IB2 within Rack 4
R4-IB2-P8A to R4-IB1-P3B
3 meters
R4 IB2 to Rack 1
R4-IB2-P10B to R1-IB1-P8B
10 meters
R4 IB2 to Rack 2
R4-IB2-P11A to R2-IB1-P9B
5 meters
R4 IB2 to Rack 3
R4-IB2-P11B to R3-IB1-P10B
5 meters
R4 IB2 to Rack 5
R4-IB2-P8B to R5-IB1-P4B
5 meters
R4 IB2 to Rack 6
R4-IB2-P9A to R6-IB1-P5B
5 meters
R4 IB2 to Rack 7
R4-IB2-P9B to R7-IB1-P6B
10 meters
R4 IB2 to Rack 8
R4-IB2-P10A to R8-IB1-P7B
10 meters

The following table shows the cable connections for the fifth spine switch (R5-IB1) when cabling eight full racks together.

Table 121  Leaf Switch Connections for the Fifth Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R5 IB3 within Rack 5
R5-IB3-P8A to R5-IB1-P3A
3 meters
R5 IB3 to Rack 1
R5-IB3-P10A to R1-IB1-P7A
10 meters
R5 IB3 to Rack 2
R5-IB3-P10B to R2-IB1-P8A
10 meters
R5 IB3 to Rack 3
R5-IB3-P11A to R3-IB1-P9A
5 meters
R5 IB3 to Rack 4
R5-IB3-P11B to R4-IB1-P10A
5 meters
R5 IB3 to Rack 6
R5-IB3-P8B to R6-IB1-P4A
5 meters
R5 IB3 to Rack 7
R5-IB3-P9A to R7-IB1-P5A
5 meters
R5 IB3 to Rack 8
R5-IB3-P9B to R8-IB1-P6A
10 meters
R5 IB2 within Rack 5
R5-IB2-P8A to R5-IB1-P3B
3 meters
R5 IB2 to Rack 1
R5-IB2-P10A to R1-IB1-P7B
10 meters
R5 IB2 to Rack 2
R5-IB3-P10B to R2-IB1-P8B
10 meters
R5 IB2 to Rack 3
R5-IB2-P11A to R3-IB1-P9B
5 meters
R5 IB2 to Rack 4
R5-IB2-P11B to R4-IB1-P10B
5 meters
R5 IB2 to Rack 6
R5-IB2-P8B to R6-IB1-P4B
5 meters
R5 IB2 to Rack 7
R5-IB2-P9A to R7-IB1-P5B
5 meters
R5 IB2 to Rack 8
R5-IB2-P9B to R8-IB1-P6B
10 meters

The following table shows the cable connections for the sixth spine switch (R6-IB1) when cabling eight full racks together.

Table 122  Leaf Switch Connections for the Sixth Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R6 IB3 within Rack 6
R6-IB3-P8A to R6-IB1-P3A
3 meters
R6 IB3 to Rack 1
R6-IB3-P9B to R1-IB1-P6A
10 meters
R6 IB3 to Rack 2
R6-IB3-P10A to R2-IB1-P7A
10 meters
R6 IB3 to Rack 3
R6-IB3-P10B to R3-IB1-P8A
5 meters
R6 IB3 to Rack 4
R6-IB3-P11A to R4-IB1-P9A
5 meters
R6 IB3 to Rack 5
R6-IB3-P11B to R5-IB1-P10A
5 meters
R6 IB3 to Rack 7
R6-IB3-P8B to R7-IB1-P4A
5 meters
R6 IB3 to Rack 8
R6-IB3-P9A to R8-IB1-P5A
5 meters
R6 IB2 within Rack 6
R6-IB2-P8A to R6-IB1-P3B
3 meters
R6 IB2 to Rack 1
R6-IB2-P9B to R1-IB1-P6B
10 meters
R6 IB2 to Rack 2
R6-IB3-P10A to R2-IB1-P7B
10 meters
R6 IB2 to Rack 3
R6-IB2-P10B to R3-IB1-P8B
5 meters
R6 IB2 to Rack 4
R6-IB2-P11A to R4-IB1-P9B
5 meters
R6 IB2 to Rack 5
R6-IB2-P11B to R5-IB1-P10B
5 meters
R6 IB2 to Rack 7
R6-IB3-P8B to R7-IB1-P4B
5 meters
R6 IB2 to Rack 8
R6-IB2-P9A to R8-IB1-P5B
5 meters

The following table shows the cable connections for the seventh spine switch (R7-IB1) when cabling eight full racks together.

Table 123  Leaf Switch Connections for the Seventh Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R7 IB3 within Rack 7
R7-IB3-P8A to R7-IB1-P3A
3 meters
R7 IB3 to Rack 1
R7-IB3-P9A to R1-IB1-P5A
10 meters
R7 IB3 to Rack 2
R7-IB3-P9B to R2-IB1-P6A
10 meters
R7 IB3 to Rack 3
R7-IB3-P10A to R3-IB1-P7A
10 meters
R7 IB3 to Rack 4
R7-IB3-P10B to R4-IB1-P8A
10 meters
R7 IB3 to Rack 5
R7-IB3-P11A to R5-IB1-P9A
5 meters
R7 IB3 to Rack 6
R7-IB3-P11B to R6-IB1-P10A
5 meters
R7 IB3 to Rack 8
R7-IB3-P8B to R8-IB1-P4A
5 meters
R7 IB2 within Rack 7
R7-IB2-P8A to R7-IB1-P3B
3 meters
R7 IB2 to Rack 1
R7-IB2-P9A to R1-IB1-P5B
10 meters
R7 IB2 to Rack 2
R7-IB3-P9B to R2-IB1-P6B
10 meters
R7 IB2 to Rack 3
R7-IB2-P10A to R3-IB1-P7B
10 meters
R7 IB2 to Rack 4
R7-IB2-P10B to R4-IB1-P8B
10 meters
R7 IB2 to Rack 5
R7-IB2-P11A to R5-IB1-P9B
5 meters
R7 IB2 to Rack 6
R7-IB3-P11B to R6-IB1-P10B
5 meters
R7 IB2 to Rack 8
R7-IB3-P8B to R8-IB1-P4B
5 meters

The following table shows the cable connections for the eighth spine switch (R8-IB1) when cabling eight full racks together.

Table 124  Leaf Switch Connections for the Eighth Rack in an Eight-Rack System
Leaf Switch
Connection
Cable Length
R8 IB3 within Rack 8
R8-IB3-P8A to R8-IB1-P3A
3 meters
R8 IB3 to Rack 1
R8-IB3-P8B to R1-IB1-P4A
10 meters
R8 IB3 to Rack 2
R8-IB3-P9A to R2-IB1-P5A
10 meters
R8 IB3 to Rack 3
R8-IB3-P9B to R3-IB1-P6A
10 meters
R8 IB3 to Rack 4
R8-IB3-P10A to R4-IB1-P7A
10 meters
R8 IB3 to Rack 5
R8-IB3-P10B to R5-IB1-P8A
5 meters
R8 IB3 to Rack 6
R8-IB3-P11A to R6-IB1-P9A
5 meters
R8 IB3 to Rack 7
R8-IB3-P11B to R7-IB1-P10A
5 meters
R8 IB2 within Rack 8
R8-IB2-P8A to R8-IB1-P3B
3 meters
R8 IB2 to Rack 1
R8-IB2-P8B to R1-IB1-P4B
10 meters
R8 IB2 to Rack 2
R8-IB3-P9A to R2-IB1-P5B
10 meters
R8 IB2 to Rack 3
R8-IB2-P9B to R3-IB1-P6B
10 meters
R8 IB2 to Rack 4
R8-IB2-P10A to R4-IB1-P7B
10 meters
R8 IB2 to Rack 5
R8-IB2-P10B to R5-IB1-P8B
5 meters
R8 IB2 to Rack 6
R8-IB3-P11A to R6-IB1-P9B
5 meters
R8 IB2 to Rack 7
R8-IB3-P1B to R7-IB1-P10B
5 meters