SPARC SuperCluster T4-4 Owner's Guide

Exit Print View

Updated: February 2016
 
 

Network Connection Requirements for SPARC SuperCluster T4-4

The following connections are required for a SPARC SuperCluster T4-4 installation:

Table 1  New Network Connections Required for Installation
Connection Type
Number of connections
Comments
Management network
1 for Ethernet switch
Connect to the existing management network
Client access network
Typically 1–2 per SPARC T4‐4 server:
  • Full rack: typically 4–8 connections

  • Half rack: typically 2–4 connections

Connect to the client access network. (You will not have redundancy through IPMP if there is only one connection per SPARC T4-4.)