Consider the following when selecting a location for the new rack.

  • Do not install the rack in a location that is exposed to:

    • Direct sunlight

    • Excessive dust

    • Corrosive gases

    • Air with high salt concentrations

    • Frequent vibrations

    • Sources of strong radio frequency interference

    • Static electricity

  • Use power outlets that provide proper grounding.

    • A qualified electrical engineer must perform any grounding work.

    • Each grounding wire for the rack must be used only for the rack.

    • The grounding resistance must not be greater than 10 ohms.

    • Verify the grounding method for the building.

  • Observe the precautions, warnings, and notes about handling that appear on labels on the equipment.

  • (CHECKLIST) Operate the air conditioning system for 48 hours to bring the room temperature to the appropriate level.