Preparing to Upgrade Clustered Controllers (BUI)
Use the following procedure to prepare to upgrade clustered
controllers.
Before You Begin
Complete Preparing for a Software Upgrade.
Note -
For the purpose of this procedure, the first controller to be upgraded
is referred to as controller A and its peer is controller B. If one of
the controllers is in a Stripped state (it has no active resources),
upgrade that controller first to avoid availability delays. If both
controllers in a cluster have active resources, choose either controller
to upgrade first.
-
On your local system, download the software update as described in
Checking for and Downloading Software Updates (BUI).
The update package is a single compressed file named with the version
number, such as ak-nas-2013-06-05-0-0.0.pkg.gz. You
can rename the file if needed; the version number is recorded within the
image. The updates can vary in size, but are typically several hundred
megabytes in size.
-
On controller A, go to Configuration > Cluster and check the active
resources and status of each peer.
For information about the cluster states, see Cluster Takeover and Failback in Oracle ZFS Storage Appliance Administration Guide, Release OS8.7.0.
-
If the management interface is unlocked
, click the lock icon
next to the management interface.
-
Go to Maintenance > System and click the add icon
next to Software Updates.
-
In the Add Software Update box, browse and select the update you want
to install.
A progress bar is displayed showing the progress of the upload.
-
Repeat steps 2-5 on controller B.