Go to main content
Oracle® SuperCluster T5-8 Owner's Guide

Exit Print View

Updated: May 2016
 
 

Sun Datacenter InfiniBand Switch 36 Switches

Each Oracle SuperCluster T5-8 contains three Sun Datacenter InfiniBand Switch 36 switches, in either the Full Rack or Half Rack version, two of which are leaf switches (the third is used as a spine switch to connect two racks together). The two leaf switches are connected to each other to provide redundancy should one of the two leaf switches fail. In addition, each SPARC T5-8 server, Exadata Storage Server, and ZFS storage controller has connections to both leaf switches to provide redundancy in the InfiniBand connections should one of the two leaf switches fail. For more information, see Understanding the Physical Connections.