Oracle® SuperCluster M8 and SuperCluster M7 Installation Guide

Exit Print View

Updated: January 2019
 
 

Two-Rack Cabling

This table shows the cable connections for the first spine switch (R1-U1) when cabling two full racks together.

Table 30  Leaf Switch Connections for the First Rack in a Two-Rack System 
Leaf Switch
Connection
Cable Length
R1-U24 within Rack 1
R1-U24-P8A to R1-U1-P3A
R1-U24-P8B to R1-U1-P4A
R1-U24-P9A to R1-U1-P5A
R1-U24-P9B to R1-U1-P6A
3m
R1-U24 to Rack 2
R1-U24-P10A to R2-U1-P7A
R1-U24-P10B to R2-U1-P8A
R1-U24-P11A to R2-U1-P9A
R1-U24-P11B to R2-U1-P10A
5m
R1-U18 within Rack 1
R1-U18-P8A to R1-U1-P3B
R1-U18-P8B to R1-U1-P4B
R1-U18-P9A to R1-U1-P5B
R1-U18-P9B to R1-U1-P6B
3m
R1-U18 to Rack 2
R1-U18-P10A to R2-U1-P7B
R1-U18-P10B to R2-U1-P8B
R1-U18-P11A to R2-U1-P9B
R1-U18-P11B to R2-U1-P10B
5m

This table shows the cable connections for the second spine switch (R2-U1) when cabling two full racks together.

Table 31  Leaf Switch Connections for the Second Rack in a Two-Rack System
Leaf Switch
Connection
Cable Length
R2-U24 within Rack 2
R2-U24-P8A to R2-U1-P3A
R2-U24-P8B to R2-U1-P4A
R2-U24-P9A to R2-U1-P5A
R2-U24-P9B to R2-U1-P6A
3m
R2-U24 to Rack 1
R2-U24-P10A to R1-U1-P7A
R2-U24-P10B to R1-U1-P8A
R2-U24-P11A to R1-U1-P9A
R2-U24-P11B to R1-U1-P10A
5m
R2-U18 within Rack 2
R2-U18-P8A to R2-U1-P3B
R2-U18-P8B to R2-U1-P4B
R2-U18-P9A to R2-U1-P5B
R2-U18-P9B to R2-U1-P6B
3m
R2-U18 to Rack 1
R2-U18-P10A to R1-U1-P7B
R2-U18-P10B to R1-U1-P8B
R2-U18-P11A to R1-U1-P9B
R2-U18-P11B to R1-U1-P10B
5m