Install the Server Top Cover

  1. Place the top cover on the chassis.

    Set the cover down so that it hangs over the rear of the server by about 1 inch (25 mm) and the side latches align with the cutouts in the chassis.

  2. Check both sides of the chassis to ensure that the top cover is fully down and flush with the chassis.

    If the cover is not fully down and flush with the chassis, slide the cover towards the rear of the chassis to position the cover in the correct position.


    Caution

    Caution  -  If the top cover is not correctly positioned before you attempt to latch the cover, the internal latch that is located on the underside of the cover might be damaged.


  3. Gently slide the cover toward the front of the chassis until it latches into place (with an audible click).

    As you slide the cover toward the front of the server, watch the green release button. You will hear an audible click when the green release button pops up, indicating that the cover is locked.


    image:Figure showing the server top cover being installed.