Connect the SFP+ Cables

  1. Identify the prerequisite and subsequent installation tasks that you must perform in conjunction with this task.

    See Installation Task Overview.

  2. Remove the protective cap from the connector or transceiver and visually inspect the cable connector.

    The shell should not be bent and should be parallel to the inner boards. If the connector is bent or damaged, use a different cable.

  3. Ensure that the retraction strap is folded back against the cable.
  4. Orient the cable connector to the SFP+ receptacle squarely and horizontally.

    Ensure that the L groove is up for the top row of receptacles, or that the L groove is down for the bottom row of receptacles.


    image:Illustration shows the IB cable being attached.
  5. Slowly move the connector in.

    As you slide the connector in, the shell should be in the center of the SFP+ receptacle.

    • If the connector stops or binds after about 1/4 in. (5 mm) travel, back out and repeat from Step 4.
    • If the connector stops or binds with about 1/8 in. (2 mm) still to go, back out and repeat Step 5.
  6. Continue to push the connector in until you feel a detent.
  7. Lay the cable into a slot on the CMB.
  8. Repeat Step 2 through Step 7 for each cable to be connected.
  9. Secure the cables to the CMB.

    See Secure Cables to the CMB.