Identify the prerequisite and subsequent installation tasks that you must
perform in conjunction with this task.
See Installation Task Overview.
-
Consider your next step.
-
If the SER MGT cable will be a full-time connection, go to Step 3.
-
If the SER MGT connection will only be temporary for installation, go
to Step 5.
-
Pass the end of the SER MGT cable through the opening on the side of the air
duct assembly.
-
If the SER MGT cable is on the left, pass the cable from the outside,
through the opening on the left side (no Oracle logo) in to the
center.
-
If the SER MGT cable is on the right, pass the cable from the outside,
through the opening on the right side (Oracle logo) in to the center.
-
Continue to pull the cable through the air duct assembly to take up the
slack.
-
Orient the RJ-45 connector to the SER MGT receptacle at the front of the
switch, adjacent to the left power supply.
The tab is up for the receptacle.
-
Insert the connector into the receptacle until it clicks, securing it in
place.
-
Connect the other end of the SER MGT cable to a serial device.
See Connect a Serial Management Device to the SER MGT Port.