Connect the Power Cords

  1. Identify the prerequisite and subsequent installation tasks that you must perform in conjunction with this task.

    See Installation Task Overview.

  2. Ensure that the circuit breakers for the facility power receptacle or power distribution device are switched off.
  3. Plug the power cords into the receptacles at the front of the switch chassis.
    image:Illustration shows the power cords being attached.
  4. Plug each power cord into the facility power receptacle or power distribution device.

    Note -  To provide redundancy, connect each power cord to a separate power source. The switch can operate with only one power source, but there is no redundancy in that case.

    Caution

    Caution  -  Do not apply power at this time.


  5. Consider your next steps.