Prepare the Air Duct Assembly


Note -  Both the cover and air duct are symmetrical, and have no defined top or bottom. If the cover has a logo, that logo goes to the right.
  1. Identify the prerequisite and subsequent installation tasks that you must perform in conjunction with this task.

    See Installation Task Overview.

  2. Align the large opening of the air duct with the mesh on the back side of the cover.
    image:The illustration shows the air duct being inserted into the                             cover.
  3. Press the air duct into the cover, to make a firm friction fit.
  4. Install the cage nuts into the rack.

    See Install the Cage Nuts.