Assemble the following resources before installing the server:
Two or more people to unpack, move, and install the server
Antistatic wrist strap, required when installing or servicing components (included in shipping kit)
T25 Torx screwdriver, used to unpack the PDUs from shipping brackets (included in shipping kit)
6-mm hexagon key or driver, used when unpacking the server from shipping pallet (included in the rack shipping kit)
8-mm hexagon key or driver, used when unpacking the server from the Oracle Rack Cabinet 1242 shipping pallet (included in the rack shipping kit)
17-mm wrench, used when unpacking the server from shipping pallet (included in rack shipping kit)
12-mm wrench, used to lower or raise the Sun Rack II leveling feet (included in Sun Rack II shipping kit)
cage nut tool, optionally used to install cage nuts into the RETMA rails
Plastic tie-downs and tie-wraps to secure cables
A tool to cut plastic strapping tape on the shipping container
Tools specific for rackmounted servers:
Forklift, pallet jack, or trolley to move packaged server to the unpacking area
3/16-inch (4.8-mm) A36 metal plate with beveled edges that is large enough to bridge gaps in the floor
Eight bolts and washers to secure the server to the floor (optional)
In addition, you must provide a system console device, such as one of the following:
ASCII terminal, workstation, or laptop
Terminal server
Patch panel connected to a terminal server