Server Upgrade Process

The SPARC T5-8 server supports two configurations:

  • Fully-populated — four processor modules

  • Half-populated — two processor modules and two processor filler modules

Processor modules and processor filler modules are cold-service components that can be replaced only after you remove all power from the system. For the location of the processor modules, see Front Panel Components (Service).


Caution

Caution  -  This procedure requires that you handle components that are sensitive to electrostatic discharge. This discharge can cause server components to fail.


This table contains the steps for upgrading the server to a fully-populated configuration. You can also view an animated demonstration of the upgrade process at:

Step
Description
Link
1.
Remove the upgrade components from their packaging, and place them on an antistatic mat.
2.
Remove the covers from the new processor modules.
3.
Remove all of the DIMM filler panels in the processor modules. The steps to remove DIMM filler panels are the same as the steps for removing DIMMs.
4.
Install the DIMMs. All of the DIMMs must be either 16 or 32 GB, and they must match the size and capacity of the DIMMs that are already installed in the server.
5.
Replace the covers on the new processor modules.
6.
Check for faults. If any fault is present, you must correct the fault and clear it from the server.
7.
Shut down the server.
8.
Remove the processor filler modules from slot 1 and slot 2.
9.
Install the new processor modules in slot 1 and slot 2.
10.
Return the server to operation.
11.
Check for faults. If any fault is present, you must correct the fault and clear it from the server.
12.
Review the root complex changes.
13.
Review the PCIe card load balancing changes. Even though the load balancing guidelines change with the upgrade, you do not need to move any existing PCIe cards.